| Attachment F - 2009 DWSRF Primary Project List - 3/16/09 | ||||||||
| Total Points[1] | Name | PWSID | Description | Purpose | Requested Loan Amount | Population | ||
| 178 | Princeton Water District | 92388 | Transmission Main to Consolidate | Resolve Acute Contamination | $412,800.00 | 75 | ||
| 156 | Aqua Maine - Camden-Rockland | 90300 | Water Treatment Plant | Resolve Non-Acute Contamination | $3,621,868.00 | 18185 | ||
| 152 | Southwest Harbor Water Depart | 91490 | Treatment - Add Aeration, move intake | DBP Reduction | $477,000 | 2313 | ||
| 149 | St. Francis Water District | 91390 | New Source | Resolve DBPs | $349,423 | 80 | ||
| 138 | Auburn Water District | 90070 | Design of New WTF | Compliance with LT2ESWTR | $250,000.00 | 15625 | ||
| 137 | Sanford Water District | 91415 | Tank Mixing & Tea-Bagging Disinfection | Compliance with TCR Rule, improve water quality. | $200,000 | 14463 | ||
| 130 | Auburn Water District/City of Lewiston | 90070 & 90830 | Construct New Water Treatment Facility Phase I | Compliance with LT2ESWTR | $1,935,450.00 | 38750 | ||
| 126 | Richmond Utilities District | 91370 | Backup Well & Tank Circulation | Redundancy and Tank Circulation | $226,000.00 | 1370 | ||
| 125 | Presque Isle Water District | 91310 | UV Treatment Unfiltered Source | Compliance with LT2ESWTR | $560,000.00 | 5973 | ||
| 122 | Brewer Water Department | 90220 | Provide Redundant Facilities | Interconnection with Adjacent Water System | $418,000.00 | 8750 | ||
| 120 | Livermore Falls Water District | 90880 | Water main replacement | Replace Aging Infrastructure | $1,558,560.00 | 3275 | ||
| 120 | Portland Water District | 91300 | Water Main Replacement Project No. 1 | Replace Aging Infrastructure | $184,186.50 | 124258 | ||
| 116 | Nichols Mobile Home Park | 7378 | New Supply | Resolve Non-Acute Contamination(Uranium) | $120,666 | 75 | ||
| 115 | Bangor Water District | 90110 | Conceptual Study on LT2 | Compliance with LT2ESWTR | $236,000.00 | 27500 | ||
| 114 | Portland Water District | 91300 | Water Main Replacement Project No. 5 | Replace Aging Infrastructure | $380,205.00 | 124258 | ||
| 113 | Portland Water District | 91300 | Water Main Replacement Project No. 2 | Replace Aging Infrastructure | $161,608.80 | 124258 | ||
| 111 | Kennebec Water District | 90750 | Water Main Replacement | Replace Aging Infrastructure | $522,240.00 | 22438 | ||
| 110 | Orono-Veazie Water District | 91210 | Water Treatment Plant Upgrades | Operational Efficiency | $3,600,000.00 | 5500 | ||
| 110 | Port Clyde Water District | 91290 | Booster Station | Resolve Low Pressure Problems | $158,000.00 | 338 | ||
| 109 | Bowdoinham Water District | 90210 | New Well | Provide Redundant Supply Well | $149,940.00 | 700 | ||
| 109 | Brownville Water Department | 90240 & 90250 | Backup Power for two well house | Redundant Power Supply | $87,000.00 | 1178 | ||
| 108 | Portland Water District | 91300 | Water Main Replacement Project No. 11 | Replace Aging Infrastructure | $386,197.50 | 124258 | ||
| 108 | Portland Water District | 91300 | Storage Tank Rehabilitation-Coating Syste | Rehabilitation of Infrastructure | $400,000.00 | 124258 | ||
| 108 | Sanford Water District | 91413 | Station Upgrades | Improve Safety and Provide Emergency Power | $714,100 | 14463 | ||
| 108 | Passamaquoddy Water District | 90510 | Treatment & GW Source Study | Resolve DBPs | $57,000.00 | 2250 | ||
| 106 | Madawaska Water District | 90920 | Replace Booster PS & PSV Equipment | Address Aging Infrastructure & Low Pressure | $313,900 | 2863 | ||
| 106 | Searsport Water District | 91440 | Well rehabilitation | Rehabilitate sole source well | $15,045.00 | 2500 | ||
| 105 | Brewer Water Department | 90220 | Provide Redundant Facilities | Redundant Intake Structure | $247,350.00 | 8750 | ||
| 105 | Brunswick & Topsham Water District | 90260 | Treatment Facility Upgrades | Compliance with Stage 2 D/DBP | $663,000.00 | 17250 | ||
| 105 | Portland Water District | 91300 | Water Main Replacement Project No. 12 | Replace Aging Infrastructure | $136,654.50 | 124258 | ||
| 104 | Southwest Harbor Water Depart | 91490 | Emergency Generation for two locations | Back-up power generation | $400,000 | 2313 | ||
| 103 | Old Town Water District | 91200 | Treatment Facility Upgrades | Rehabilitate Aging Infrastructure-enhance treatment | $584,205.00 | 7500 | ||
| 103 | Portland Water District | 91300 | Water Main Replacement Project No. 3 | Replace Aging Infrastructure | $380,205.00 | 124258 | ||
| 102 | Portland Water District | 91300 | Water Main Replacement Project No. 4 | Replace Aging Infrastructure | $297,075.00 | 124258 | ||
| 100 | Gardiner Water District | 90610 | Water Main Replacement | Replace Aging Infrastructure | $678,276 | 8265 | ||
| 96 | Aqua Maine - Camden-Rockland | 90300 | New Storage Tank | Replace Aging Infrastructure | $990,379.00 | 18185 | ||
| 95 | Bangor Water District | 90110 | Water Storage Tank Replacement | Aging Infrastructure and Improved Water Quality | $1,850,790.00 | 27500 | ||
| 95 | Greater Augusta Utility District | 90080 | Water Main Replacement | Replace Aging Infrastructure | $285,250.00 | 14450 | ||
| 94 | Auburn Water District | 90070 | Water Main Rehabilitation & Improvements | Address Aging Infrastructure | $875,160.00 | 15625 | ||
| 94 | Berwick Water Department | 90150 | Water Main Replacement | Replace Aging Infrastructure | $674,097.60 | 2250 | ||
| 94 | Berwick Water Department | 90150 | Water Main Replacement | Replace Poorly Constructed Infrastructure | $212,731.20 | 2250 | ||
| 94 | Berwick Water Department | 90150 | Water Main Replacement | Low Pressure & Replacement of Aging Infrastructure | $149,226.00 | 2250 | $1,728,665.40 | |
| 94 | City of Calais | 90290 | Water Main Replacement | Replace Aging Infrastructure & Address Low Pressure | $261,000.00 | 3075 | ||
| 94 | Great Salt Bay Sanitary District | 90410 | Water Main Replacement | Replace Aging Infrastructure | $45,640 | 1750 | ||
| 94 | Lake Arrowhead Community | 90811 | Water Main Replacement | Replace Aging Infrastructure | $180,000.00 | 3250 | ||
| 93 | Portland Water District | 91300 | Water Main Replacement Project No. 10 | Replace Aging Infrastructure | $481,261.50 | 124258 | ||
| 92 | Portland Water District | 91300 | Water Main Replacement Project No. 8 | Replace Aging Infrastructure | $338,665.50 | 124258 | ||
| 92 | Portland Water District | 91300 | Water Main Replacement Project No. 13 | Replace Aging Infrastructure | $53,473.50 | 124258 | ||
| 91 | Portland Water District | 91300 | Water Main Replacement Project No. 16 | Replace Aging Infrastructure | $120,000.00 | 124258 | ||
| 91 | Yarmouth Water District | 91670 | Water Main Replacement | Replace Aging Infrastructure | $807,746 | 7450 | ||
| 91 | Rumford Water District | 91380 | Transmission main replacement | Replace Aging Infrastructure | $534,786.00 | 4323 | ||
| 91 | Passamaquoddy Water District | 90510 | Water Main Replacement | Aging Infrastructure | $1,500,000.00 | 2250 | ||
| 90 | Bath Water District | 90130 | Water Main Looping | Resolve Dead Ends | $800,700.00 | 9177 | ||
| 90 | Belfast Water District | 9014 | Water Main Replacement | Replace Aging Infrastructure | $1,306,000.00 | 4885 | ||
| 90 | Berwick Water Department | 90150 | Emergency Infrastructure | Backup Systems for Emergency Response | $448,800.00 | 2250 | ||
| 90 | Berwick Water Department | 90150 | Water Main Replacement | Reduce Velocity in a high pressure line | $243,810.60 | 2250 | ||
| 87 | Portland Water District | 91300 | Water Main Replacement Project No. 7 | Replace Aging Infrastructure | $463,437.00 | 124258 | ||
| 87 | Portland Water District | 91300 | Transmission Main Project No. 17 | Redundant Transmission Lines & Reslove l | $724,200.00 | 124258 | ||
| 86 | Bingham Water District | 90180 | Water Main Replacement & Looping | Replace Aging Infrastructure & Improve Water Quality | $334,000.00 | 1308 | ||
| 86 | Pittsfield Water Works | 91280 | Install Finished Water Pump at Treatment | For Redundant Pumping Systems | $103,020.00 | 3235 | ||
| 85 | Auburn Water District/City of Lewiston | 90070 & 90830 | Construct New Water Treatment Facility Phase II | Compliance with LT2ESWTR | $5,806,350.00 | 38750 | ||
| 2009 Final Primary Project List - Attachment F.xls | Available Funds = $40,137,992 | Total = | $37,683,419 | |||||
| Note: | The last project on the list (Auburn/Lewiston Phase II) lacks $334,488 to be fully funded. | |||||||
| The following projects have been removed from the project list due to finding other funding sources, or the projects have already been completed. | ||||||||