Updated Construction Advertisement Schedule

Presented below you will find:

  1. The Updated Construction Advertisement Schedule refreshed every monday
  2. Current Schedule Performance, listing the current status of all projects included in the annual Construction Advertisement Plan, as well as any projects that have been added to the schedule this year (pdf below)
  3. A Current Schedule Performance chart, based on the annual Construction Advertisement Plan, published in January of each year
  4. A searchable Project Map, which can also be accessed by selecting the "View Map" links within tab 1
  5. The Glossary with descriptions of the Change Status and Work Types used in the Advertisement Schedule

Searchable Project Map

View our searchable Project Map to find projects by town or county.

PDF Downloads

If you have a problem accessing this data, please contact Jerry Casey at 207-624-3344 or jerry.casey@maine.gov .

Updated Construction Advertisement Schedule

Select a column title (arrow) to sort by Work Type, Advertise Date, Location/Title/Details, Project Identification No., or Estimated Construction Cost Range. The initial sort order is by Advertise Date, Work Type, and Location/Title.

Work Type Advertise Date Location/Title/Details Project
Identification No.
Estimated Construction Cost Range

back to top

Current Status of Annual Construction Advertisement Plan
Number of Projects =

Status of Projects in Plan

skip to projects in plan chart table
Project StatusNumber of Projects

Status of Projects Added
Total Number of Projects Added:

skip to projects in plan chart table
Project StatusNumber of Projects

Glossary

Work Type Descriptions

Work Type Description
Bridge Construction Construction, replacement or major rehabilitation of traditional bridges and minor spans that are not culverts, including superstructure and deck replacements.
Bridge Other All other bridge projects, including preservation and replacement of large culvert-like structures defined as bridges or minor spans.
Highway Construction Construction on new alignment, reconstruction, or major rehabilitation of a road corridor that generally involve changes to the alignment or width of the road. Sometimes known in the industry as “dirt jobs”.
Highway Safety and Spot Improvements Intersection and ramp improvements, as well as signing, lighting, striping, etc. May include substantial, higher cost, intersection construction projects.
Highway Preservation Paving All pavement preservation or rehabilitation treatments of higher priority roads, designed to maintain a higher level of service and avoid the higher cost of reconstruction. The useful life of such treatments is generally 10 years or more. Does not include Light Capital Paving (see below).
Highway Light Capital Paving (LCP) A thin pavement treatment to keep poor, generally lesser traveled roads serviceable. The useful life of LCP paving is about 4 to 7 years. Formerly known as Maintenance Surface Treatment (MST) or “skinny-mix”.
Multimodal Rail, transit, airport, marine, and bicycle/pedestrian projects.

Status Descriptions

Status Description
Advertised On Time Project is in the annual plan and was advertised within 29 days of planned date.
On Time Project is in the annual plan, not yet advertised, and the current forecast advertise date is within 29 days of the planned date.
Advertised Late Project is in the annual plan and was advertised 30 days or more after the planned date.
Merged with Other Work Project is part of the annual plan and now included in the scope of another project in order to reduce administrative costs.
Removed from Schedule Project was in the annual plan but has been removed from the schedule.
Delayed Project is in the annual plan and the current advertisement forecast date is 30 days or more after the planned date, or, there is no actual advertisement date within 29 days of the planned date.