Skip Maine state header navigation
I. INTRODUCTION
A. Report
Process
During its
2004 session, the Legislature enacted The Maine Wind Energy Act, P.L. 2003, ch
665, §§3,4 (the “Act”). As part of that
Act, the Legislature directed the Public Utilities Commission (“Commission”) to
conduct a study of the viability of and potential for the development of wind
power in the State. In particular, the
Act specifies that the study should examine the realistic potential for wind
power development in Maine, the cost of wind power, potential markets, impacts
of wind power on the electric grid, potential for siting wind facilities on
tribal lands, and obstacles to wind power development in the State.
In
conducting its study, the Commission held interviews and meetings with a wide
variety of entities having expertise or interest in issues involving wind power
and renewable resources, including discussions with wind power developers,
utilities, grid system operators, environmental groups, wind power opponents,
tribal representatives, and other state agencies.[1] The Commission also conducted extensive
research on a variety of wind power and renewable resource issues. Finally, to solicit input from the public,
the Commission released a draft report and sought written comment on the draft
from all interested parties.[2]
The
results of the Commission study are contained in this report. The report is structured as follows:
§
Section II – Wind Power Potential: Review of the major considerations in determining
whether a particular site is viable for wind power development and presentation
of estimates of wind power potential in the State.
§
Section III – Cost of Wind Power: Description of the cost of developing wind power and
its economics relative to conventional generation resources.
§
Section IV – Available Markets: Discussion of potential markets for wind power developed in Maine in
New England states and neighboring Canadian provinces.
§
Section V – System Implications: Discussion of the implications of wind power
development on overall system reliability, market operations, air emissions and
existing generating facilities.
§
Section VI – Obstacles to Wind Power Development: Presentation of the major obstacles to wind power
development in the State.
§
Section VII – Siting of Wind Power on Tribal Lands: Discussion of the potential for wind power
development on tribal lands and obstacles to that development.
§
Section VIII – Alternative Approaches to Promoting Wind
Power Development in Maine: Considerations and Recommendations: Presentation of various approaches to promoting wind
power development, with a discussion of issues to be taken into account in
setting policy and how certain policies might best be implemented.
B. Desirability of Wind Power
The
Commission views its charge from the Legislature to be to prepare and present
an objective assessment of a variety of issues, as specified in the Act,
related to the viability of wind power and the potential for its development in
the State. The purpose of this assessment
is to provide the Legislature with an aid for determining overall State energy
policy and the available means for effective promotion of wind power if the
Legislature determines such action to be in the public interest. Although the attributes of wind power (both
positive and negative) are referred to throughout this report, the Commission
offers no conclusion as to whether the active promotion of wind power should be
a part of the State’s energy policy or whether public or ratepayer funds should
be expended to aid wind power development in Maine.
Governmental
support for wind power development is primarily justified on the basis of
environmental and system diversity benefits.
The principal environmental benefit of wind power is that it is an
electric generation source that does not produce air emissions. Enhanced system diversity tends to stabilize
and moderate electricity prices, and provide greater system security. Wind power opponents are of the view that
environmental benefits are often overstated and tend to be outweighed by negative
impacts, primarily the visual degradation of large areas of the landscape and
harm to migratory birds (and other wildlife).
Opponents also state that wind power is costly, requires public
subsidies and that air quality improvements can be better achieved through
other means, such as the promotion of energy conservation and the enhancement
of pollution controls.
The
Legislature has established State goals for substantial reductions in
greenhouse gases over time, 38 M.R.S.A. § 576.
The Commission is not an environmental agency and has no view on the
best means to achieve air quality improvements or the degree to which the State
should actively promote or use public funds to support wind power development
for purposes of meeting air quality goals.
In keeping with the Commission’s role as an economic regulation agency,
however, this report does comment on the costs and system attributes of wind
power.
The Legislature, through the Maine Wind Energy Act,
has adopted a policy on wind power.
Specifically, the Act states:
The Legislature finds that it is in the public interest to explore opportunities for and encourage the development, where appropriate, of wind energy production in the State in a manner that is consistent with high environmental standards and that achieves reliable, cost-effective, sustainable energy production on those sites in the State that will attract investment and permit the development of viable wind energy projects. The Legislature finds that the development of the wind energy potential in the State needs to be integrated into the existing energy supply and transmission systems in a way that achieves system reliability, total capital cost-effectiveness and optimum short-term and long-term benefits to Maine people.
Further refinement of the State’s policy regarding the promotion of wind power is a question for the Legislature.
II. WIND POWER POTENTIAL
Maine
has substantial potential for the development of wind power facilities
throughout the State. There is theoretical
potential for thousands of megawatts, but the realistic potential for
development that is economic, environmentally sound and publicly acceptable is
not likely to exceed a thousand megawatts, at least for the foreseeable future.
A. Development Considerations
There are
four major considerations in determining whether a particular site is viable
for wind power development. These are:
·
Availability of
Wind Resource: The power of wind in
an area is often described in terms of its “Class,” with Class 1 having the
least power and Class 7 having the most power.[3] Typically, Class 4 has been considered the
minimum power necessary to support grid scale wind development. However, because of Maine’s specific wind
climate as well as improved technology, Class 3 areas in Maine may be
considered viable production sites.
While the relationship of wind speed to resource class varies, in
general, an average wind speed of 15 mph or greater at a minimum height of 70 meters
(230 feet) is necessary to support grid scale facilities.
·
Proximity to
Suitable Transmission: Generally,
sites within 5 miles of transmission facilities are desirable and those beyond
10 miles are not economically attractive because of the cost to construct
transmission from the wind generator to the grid.[4] Moreover, the ability of existing
transmission facilities to transport additional power can be a factor.
·
Environmental
Sensitivity and Other Physical Characteristics: Areas that are environmentally sensitive (e.g.
wetlands and bird migration routes) are generally not feasible because of the
costs of mitigating the environmental impact.
In addition, some areas are unsuitable for wind development due to
physical characteristics or topography.
·
Public
Acceptance: Some areas are not feasible because the generation
facilities cause impacts that are unacceptable to citizens and that cannot be
mitigated in any way (e.g., visual impact or land use that is incompatible with
local or State guidelines).
There are some differences of opinion as to the
optimal type of area for wind power development in Maine. Traditionally, mountain ridges have been
considered the primary area for wind power development in the region.[5] However, large areas of flat land (where
winds tend to blow steadily and there are fewer trees that can cause
turbulence), such as blueberry or potato fields, are also considered by some as
viable candidates for wind facilities.
Although Maine’s coastal and offshore areas have
substantial wind resources, at this time it is not likely that these areas will
be a significant source of wind development.
Such development, especially in the more southern areas of the State,
would likely be subject to significant public opposition. Moreover, the construction and maintenance
of facilities offshore is significantly more expensive than on land and the
transport of the power to the mainland could affect available fishing areas.
The number of feasible sites for wind power
development may increase with technological advances. For example, newer wind turbine technologies that require less
wind power may allow development in locations that are currently not feasible.
With more available wind development sites, developers should have more options
for locating facilities in less controversial areas.
B. Wind Potential Estimates
Wind
potential has been considered at varying levels, ranging from purely
theoretical (i.e., generating potential
if wind installations were possible wherever the wind is strong) to the
economically and politically possible (i.e., potential if generators are placed
close to the transmission grid, in areas that are less environmentally
sensitive, with consideration given to objects that block the wind, and where
public opposition is likely to be low).
Publicly available information is useful as a screening tool for
developers and as general guidance for policy makers. However, the precise identification of viable sites is extremely
costly and time consuming, and has been performed primarily by developers who
consider the information to be highly proprietary. The following paragraphs summarize the most reliable data
available, at varying levels of specificity.
At the broadest level, national
and regional efforts have resulted in relatively accurate wind maps that display
wind speeds at 30 meters (98 feet), 50 meters (164 feet), 70 meters (230 feet),
and 100 meters (328 feet) above the ground.[6] Current grid scale wind generators require
adequate wind power at 70 meters, while small-scale generation can be constructed
with lower wind power at 30 meters. The
maps show wind power at various power densities or wind speeds. These maps do not compensate for obstacles
such as buildings or local elevation variations, which could affect wind
flow. However, they provide a picture
of the regions in which wind development could most effectively be pursued, and
also provide an initial screening mechanism for developers. Not surprisingly, the maps show that the
most significant wind potential in Maine is found on the coast and on ridge
crests in the mountains. However, the
maps also show pockets of other areas with sufficient wind.[7]
In 1991, the Pacific Northwest Laboratories
determined theoretical wind potential throughout the nation by adjusting the
potential for specific areas based on geography, land-use and environmental
factors. The study estimated Maine’s
theoretical wind potential (at class 3 or higher) to be 56 billion kWhs, the
highest potential of any New England state and the 19th highest potential of
all 50 states.[8] While interesting, this estimate is of
limited practical use. It would require
approximately 18,000 MWs of wind generation, almost 10 times the electric load
in Maine or 12,000 wind turbines (typically sized at 1.5 MW), to produce that
level of generation. This is clearly
far more than can realistically be constructed.
More recently, the National Renewable Energy
Laboratory (“NREL”) analyzed wind generation potential using improved wind
speed data and newly developed Department of Energy (“DOE”) exclusions. In that
study, summarized in the chart below, NREL calculated a theoretical potential
in Maine of approximately 8,000 MWs at class 3 or higher, of which 1,000 MWs
were located within 5 miles of a transmission line.[9] A study group in Connecticut estimated that
only 25% (2,000 MWs) of the 8,000 MWs could be developed at costs reasonably
close to the current market conditions.
The Connecticut study was used in Maine’s Climate Action Plan
investigation. [10]

Finally, educated estimates from a variety of
persons familiar with the wind industry in Maine range from several hundred
megawatts to over a thousand megawatts of wind generation that might
realistically be developed in Maine.
This conclusion is generally consistent with the more recent NREL and
Connecticut studies.[11]
C. Wind Development Experience
There
are currently no large-scale wind facilities located within Maine[12]
or in New England.[13] However, there are projects currently in
various stages of development and there have been attempts to construct wind
facilities in the past. Maine wind
development experience is summarized below.
1. Mars Hill
The
wind project closest to realization is an approximately 50 MW facility located
in Mars Hill. The facility is expected
to cost in the range of $55 million and will have approximately 4 to 6
full-time employees. The facility
generally has the support of the Town of Mars Hill and of various environmental
organizations. However, an objection to
the project was raised before Maine’s Board of Environmental Protection (“BEP”)
regarding the need for preconstruction data on the risks to migratory birds and
bats. The BEP has permitted the project with various conditions, including pre-
and post-construction studies.
Construction is expected to begin in the Spring, 2005 and the facility
is expected to be operational before the end of the year.
2. Redington
Efforts
to develop
a wind project in the Redington area mountains have been under way for a number
of years. The project is expected to be
in the range of 50 MW to 90 MW. The location is considered controversial in
large part because the towers can be observed from the Appalachian Trail. Formal filings for an environmental permit and
other regulatory approvals have not yet been made.
3. Fox Island
The
Fox Island Electric Cooperative has been considering the development of wind
generation to serve the needs of the residents on the island. The Cooperative has monitored wind speeds
using a DOE grant and is considering installing wind capacity that would exceed
its customers’ electricity requirements.[14] Interconnection studies and the permitting
process have not yet begun.
4. Boundary Mountains
In
the 1990s, there was an attempt to develop a large wind facility in the
Boundary Mountains of western Maine.
The facility would have been in the range of 200 MW. The project completed most of the permitting
process and had obtained contracts to sell part of its generation to utilities
in New England. However, the developer
entered bankruptcy proceedings and the facility was never constructed.
III. COST OF WIND POWER
The
cost of wind power is competitive with the cost of other generation resources
in New England assuming the continued availability of the federal production
tax credit.
The current cost of wind power is competitive with the
cost of alternative resources in New England.[15] The installed cost of wind power has
declined rapidly over the last decade because of technological improvements and
is expected to continue to decline for some time into the future. Currently, however, the ability of wind
power to compete with other resources remains dependent on the existence of a
federal production tax credit (“PTC”) in most cases.[16]
Table
1
Similar to other types of generators, a wind facility
has development, equipment and installation costs, debt and equity costs,
taxes, and O&M costs. For wind
facilities in Maine, the Commission has been informed that capital costs are in
the range of $1,200 per kilowatt, more than double the typical capital cost of
gas-fired facilities. To put this in
perspective, a 50 MW facility at $1,200 per kilowatt would have $60 million in
capital costs. Table 1 provides an
example of the cost components of wind generation under a reasonable set of
assumptions.[17]
As
seen in Table 1, under the stated set of assumptions, the all-in, life cycle
cost for a moderately sized, grid-scale wind generation facility is between 6
and 7 ˘/kWh without the PTC. With the
PTC, however, the effective cost to a developer is between 4 and 5 ˘/kWh.[18]
Because
wind generation projects are so capital intensive, the economics are very
sensitive to the cost of financing.
Currently, the financial community is likely to demand at least an 8%
interest rate on debt to finance a privately developed wind facility.[19] As shown on Table 1, this results in a cost
of debt of approximately 1.1˘/kWh (levelized over 15 years). However, under the set of assumptions
presented here, every percentage point in the cost of debt represents
approximately 0.15 ˘/kWh. In other
words, if the interest rate is reduced from 8% to 6%, the cost of the project
over its lifetime is reduced by approximately 0.3 ˘/kWh.
Other expenses, including operation and maintenance
(“O&M”), property taxes, insurance, land lease payments and facility
maintenance are also significant and are estimated to be around 1 ˘/kWh. Of that amount, property tax is likely to be
among the largest components.[20] In addition to the costs mentioned above,
the generator must supply a profit for its equity investors. A reasonable expectation would be a 12% or
higher return -- translating to an average annual cost of 1.4˘/kWh.
Siting
studies are sometimes costly (e.g., Mars Hill’s study has cost
approximately $300,000 to date, while
the Redington project has incurred costs in excess of $2 million to date). However, those amounts are still a low percentage
of the total project cost of larger projects, adding a fraction of a cent per
kWh over 15 years (for example, under the above-described assumptions, every $1
million in extra permitting costs adds less than 0.1 ˘/kWh). Relatively large up front costs would have a
greater impact on smaller projects and those using lower wind speed sites.
Moreover, if a facility is constructed in northern Maine
and the power is sold in Canada or New England, there is a cost to transmit the
power through the transmission systems of northern Maine and (if sold in New
England) Canada. Transporting power
from northern Maine to New England can add more than
2 ˘/kWh to the cost of the power.
Actual wind power costs do vary widely from facility to
facility. A substantial factor that
drives the variability of cost per kilowatt-hour of a facility is its “capacity
factor,” which in turn is a function of the quality of the wind resource in the
area.[21] The capacity factor refers to the amount of
energy a wind facility actually generates compared with its total
capacity. There is disagreement about the
likely capacity factor of wind facilities. [22] Wind power developers expect capacity
factors of new facilities to be in the range of 30% to 40%; however, the
experience of facilities currently in operation has been significantly lower
capacity factors. Capacity factors do
not refer to the actual amount of time a
facility generates electricity. For
example, a 35% capacity factor does not mean a facility will generate 35% of
the time; the facility may generate a much greater portion of the time at lower
than maximum capacity (e.g. 70% of the time at half capacity).
Finally,
the federal PTC, which lowers the cost of generation by 1.6 to 1.8˘/kWh
(depending on the equity owner’s ability to take advantage of the credit),
appears crucial to the current economics of wind facilities. This is illustrated by the large number of
projects that were delayed until the recent renewal of the credit.[23]
As
mentioned, the cost of grid scale wind power is generally competitive with the
current cost of other resources in New England. The ability of wind power to compete with other resources depends
to a significant degree on the level of oil and gas prices; as these prices
rise, wind power becomes more economic.
Wind, which has an advantage in that its costs do not depend on
fluctuating fuel prices, can be expected to remain cost competitive into the
foreseeable future based on current fuel price expectations. Thus, larger scale
wind projects (assuming the continued existence of the federal PTC) should not
be viewed as requiring further financial assistance or subsidies to allow them
to compete on a cost basis in the current electricity market.
IV. AVAILABLE MARKETS
Sufficient markets are currently available to wind
power facilities developed in Maine and these markets are likely to remain
available into the foreseeable future.
A. State
Renewable Requirements
Maine
does not itself constitute an electricity market. Rather, southern Maine is part of the broader New England market
(i.e. ISO-NE or NEPOOL market) and northern Maine is part of the broader
Maritimes control area.[24] In addition, power is routinely traded
between the New England region and neighboring regions. Thus, all of New England, the New York
control area, the PJM control area,[25]
the Maritimes control area,[26]
and possibly Quebec represent potential markets for wind power facilities
located in Maine.
Massachusetts
and Connecticut have relatively aggressive Renewable Portfolio Standards
(“RPS”) that create an attractive market for wind power generated in Maine.[27] Both RPSs have limited eligibility criteria
that include wind power with percentage requirements that increase over
time. The increased demand caused by
these RPSs has resulted in a substantial premium for qualifying resources, such
as wind power. This premium has been in
the range of 3.5 to 5˘/kWh and a substantial premium can be expected to
continue until a significant quantity of additional eligible resources are
developed in the region. The premium is realized through the sale of what is
referred to as renewable energy credits or RECs. The use of RECs allows a wind facility to sell its “renewable
attributes” to one buyer, while selling its actual energy output to another
buyer.
Wind power facilities located in Maine are eligible for
both the Massachusetts and Connecticut RPSs. However, the Massachusetts RPS
requires that the power be delivered into ISO-NE region. Thus, wind facilities located in northern
Maine must transport their power out of northern Maine through New Brunswick
and into ISO-NE area to qualify for the Massachusetts RPS. This transmission requirement adds
significant costs[28]
that represent a barrier to accessing the Massachusetts market.[29] Connecticut does not have a delivery
requirement, making it a more readily accessible market for facilities in
northern Maine.[30]
In
addition to Massachusetts and Connecticut, other states in the region have
adopted or are considering adoption of renewable standards that would provide a
market for Maine wind power facilities. Most notably, Rhode Island has recently enacted RPS legislation
for new renewable resources that takes effect in 2007; facilities in the ISO-NE
portion of Maine would be eligible and facilities located in northern Maine
would also be eligible if the power is delivered into the ISO-NE control
area. New York has also adopted a new
renewable RPS in which wind facilities in Maine would be eligible if their
power is delivered into the New York control area.[31]
B. Canadian Markets
The
neighboring Canadian provinces of New Brunswick, Quebec, and Nova Scotia also
provide potential markets for Maine wind facilities, particularly those located
in northern Maine. In particular, New
Brunswick has recently opened its electricity markets to competition and is
required by law to adopt an RPS. Thus,
New Brunswick represents a significant potential market for Maine wind
facilities and this potential would increase if Point Lepreau (New Brunswick’s
635 MW nuclear plant) permanently closes down and New Brunswick is thus required
to acquire significant additional generation resources.
New
Brunswick is a primary market for wind facilities located in northern Maine in
that a direct connection exists.
However, power can also be transmitted through New Brunswick into Quebec
and Nova Scotia. The potential of New
Brunswick (as well as Quebec and Nova Scotia) as a market for facilities
located in the ISO-NE portion of Maine would be expanded if the currently
planned second tie-line between Maine and New Brunswick is constructed. The current tie-line between regions can
support approximately 100 MW of transactions south to north; this would be
expanded to 400 MW with the second tie line.
The current capacity north to south is in the range of 700 MW and this
would be increased to 1000 MW with the new tie-line. Thus, the construction of the second tie-line would enhance both
the ability of wind facilities located in the ISO-NE portion of Maine to sell
into New Brunswick and the ability of wind facilities located in northern Maine
to sell into the New England market.[32]
C. Green Market
Finally, a
“green market” has developed in Maine and elsewhere. A green market refers to individuals or businesses that are
willing to pay a premium for “green” or “clean” power for environmental or
other reasons. The voluntary green market provides another outlet for Maine’s
wind power that will likely grow with time, although its precise impact is
impossible to determine with any accuracy.
Wind is well positioned to benefit from a green market
because it is more universally accepted as “green” than are some other
renewable fuels. Currently, over two
thousand accounts (individual, business and governmental) are served from green
marketers. [33] While this represents less than one percent
of Maine’s consumers, improved marketing could result in wider purchases of
green power. The Legislature has
explicitly directed the Commission to inform electricity consumers in the State
of the benefits of renewable power and the opportunities to purchase
electricity generated from renewable resources.[34] In addition, the likely increase in standard
offer prices – as a result of increasing natural gas prices – may provide wind
generation more opportunities in the retail residential and small commercial
markets.
V. SYSTEM IMPLICATIONS
Wind power does not present any serious or
insurmountable grid system reliability or market operation concerns, nor is
wind power development in Maine likely to have a substantial impact on existing
generating facilities beyond those resulting from possible changes in market
prices.
A. Overview
Wind power
is not currently a significant resource in the northeastern United States and
has some characteristics that distinguish it from most other generating
resources. For these reasons, concerns
have been raised that, if wind power grows to become a significant resource in
the region, there may be substantial adverse reliability, operational, or other
system implications.
A growth of wind power in the
region at reasonably feasible levels should not result in any serious or
insurmountable reliability or operational problems. Although wind power is relatively new in the northeast, it is
quite prominent in other areas of the world and of the United States. Worldwide, there is in the range of 40,000
MW of installed wind power (about 30,000 MW in Europe and 6300 MW in the United
States). Some power systems, most
notably in Western Europe, have incorporated significant amounts of wind generation. For example, Denmark’s wind power
penetration is about 60% of its peak load, while Germany and Spain have wind
power penetrations that are 15% of their peak loads.[35] In
the United States, California (approximately 2000 MW), Texas (approximately 1300 MW), Minnesota
(approximately 560 MW), and Iowa (approximately 470 MW) have significant wind
power capacity. New Mexico has
installed wind capacity that equals approximately 15% of its peak load, and
Minnesota will soon have installed capacity equal to approximately 10% of its
total installed capacity. The American
Wind Energy Association reports that wind energy capacity in the United States
has expanded at an annual average rate of 28% over the last 5 years and
approximately 1700 MW of wind capacity was added during 2003. Thus, a substantial amount of wind power has
been integrated into electrical grids around the world and in many areas
of the country without causing insurmountable, or generally even serious,
system reliability or operational problems.
Within the
northeast, the New York ISO has completed a study that concluded that wind
power could comprise at least 10% of the system mix without reliability or
operational issues.[36] Commission discussions with representatives
of the ISO-NE and the system operator in northern Maine also revealed no
serious concerns about the potential for wind power growth in New England.
With respect to wind power development in Maine, MPS
conducted system impact studies on the Mars Hill project that revealed no major
system problems. MPS did identify the
need for some minor upgrades, the cost of which is the responsibility of the
project developer. CMP has completed a
study of the Redington project and concluded that the facility would have no
adverse impact on system reliability, but that upgrades would be required that
would be paid for the developer. Additionally, the project has received ISO-NE
approval.
B. Wind
Power Characteristics
1. Reliability
Wind
power has several characteristics that raise some system reliability
concerns. First, wind power is
intermittent in nature. As such, the
availability of wind power cannot be known with certainty. However, the system has historically
integrated intermittent resources (e.g. run-of-the-river- hydro), and load
itself is inherently unpredictable.
Moreover, newer wind turbines have a greater ability to regulate changes
in output more quickly if the system requires, and the sophistication with
which wind power output can be forecasted both on a day-ahead and an hour-ahead
basis is increasing. These developments
lessen any reliability impact caused by the intermittent nature of wind
power.
The
intermittent nature of wind power also raises a concern that there will be a
hidden cost resulting from the need for reserves or back-up power. In the New England system, however, the
amount and operation of reserves are determined as a function of the two
largest contingencies in the region (i.e. the largest available resources whose
outage would require the maximum need for reserves), which are in the range of
2000 MW and 1100 MW. Thus, even a
substantial number of wind projects of substantial size (e.g. in the range of
50 to several hundred MWs) scattered around the region are not likely to have
an impact on the cost or operation of regional reserves in New England.[37]
Another
concern regarding the nature of wind facilities is their likelihood of tripping
off line when voltage drops. This can
cause system problems depending on the size and location of the wind facility.[38] However, there are multiple ways to address
the low voltage problem (e.g. through equipment additions).[39] In addition, some wind turbine manufacturers
are claiming that new machines now have low voltage ride-through capability.
An
additional reliability concern is the relative inability of wind facilities to
control reactive power (measured in kilovars or vars). Reactive power is necessary to stabilize the
grid against voltage swings.[40] A reactive power problem, however, can be
readily addressed through the addition of equipment (e.g. capacitors). Moreover, newer wind technology is said to
have a greater ability to produce or absorb vars as needed, although the
implementation of such newer technology turbines has not yet been significant
enough to demonstrate the accuracy of such claims.
2. Energy Market Implications
The
nature of wind power as an intermittent resource has some implications for the
operation of energy markets. As a
general matter, generating facilities in the ISO-NE and northern Maine areas
are required to submit a schedule of the amount of power they will deliver into
the system a day in advance and an hour in advance, and generators suffer
monetary consequences if the actual power delivered deviates significantly from
the amount of power scheduled. However,
there are exceptions to these requirements for intermittent resources, such as
wind power. Nevertheless, current
market rules were not designed to accommodate large amounts of
intermittent resources. As a
consequence, market rules will likely be re-examined as wind power becomes a
larger part of the system.
Such
a re-examination has already occurred in some areas of the country. The PJM power pool and the California system
operator have modified their rules on power deviation charges to accommodate
intermittent power. California has also
made rule changes with respect to forecasting, scheduling and settlement. New York is in the process of re-examining its
market rules, and has also already exempted certain intermittent
resources from deviation penalties.[41]
Similarly,
the ISO-NE is expected to re-examine its rules as wind power grows in the
region.[42] The northern Maine system administrator is
likely to consider necessary changes in light of the Mars Hill project.
3. Resource Mix Implications
The
growth of wind power, due to its intermittent nature, can have certain impacts
on the development of the regional resource mix. As wind power increases, the system would tend to require less
baseload generation and more facilities with cycling or quick start
capability. Wind power cannot provide
system reserves, so reserves would have to come from other facilities. Wind facilities do have a capacity value,
but that value is significantly lower than the facility’s total capacity due to
the inherent uncertainty of wind power.[43] Over time, this could result in the need for
more generating capacity on the system than would have otherwise been required.
Assuming the generation resource market works as
designed, wind facilities would be developed in amounts that are cost effective
and would replace existing facilities that are more expensive. In this respect, wind power is no different
from other resources. Over time, the
generation resource market should respond to price signals and a least cost mix
of resources should develop. However,
the existence of renewable resource portfolio requirements in the region is
likely to have some impact on the mix of resources in a manner that would
increase overall costs relative to a system mix that would develop in the
absence of portfolio requirements.[44] This result should not be viewed as
unexpected in that the purpose of renewable resource requirements is to promote
the development of resources that would not otherwise occur due primarily to higher
costs than conventional fossil fuel facilities.
A countervailing consideration is the resource
diversity benefit of promoting wind power development in the region. Currently, around 40% of the electricity
supply in New England depends on natural gas; a situation that creates both
price and reliability risks, especially when demand is high and natural gas
supplies are low. During such times
(e.g. very cold weather), the existence of wind generation (as well as other
resources that do not depend on natural gas) would increase system reliability
and tend to lower electricity costs.
More generally, significant amounts of wind generation on the system
could provide some downward pressure on the cost of gas-fired generation by
reducing the demand for natural gas and allowing for the build-up of gas
inventories.[45]
4. Emissions Impacts
The
reduction of air emissions from electric generating plants can be considered a
primary benefit justifying the promotion of wind power development. The most direct way to view this benefit is
to consider the amount of electricity (and corresponding air emissions) that
will not be produced by other generating facilities as a result of the
production from a wind facility. In New
England, the energy that would otherwise be generated would primarily come from
gas and oil-fired facilities.[46]
However,
the precise impact of wind facilities on air emissions may require the
examination of secondary effects. For
example, the addition of a significant amount of wind power to a system could
affect the amount of capacity that must be held in reserve. If this results in an increase in generation
that must run at sub-optimal levels to provide adequate reserves, the
consequence could be a reduction in the air quality benefits from wind
power. However, such an impact in New
England is unlikely. As mentioned
above, the development of a substantial amount of wind power in the New England
region is not likely to affect the operation of reserves. Also, as discussed above, the addition of
wind power could affect the overall development of the resource mix in the
region. Because the actual impact on
system mix cannot be predicted, the secondary impacts on air emissions cannot
be determined. However, any significant
change in overall system mix would require the addition of a large amount of
wind power to the system, which would presumably be accompanied by a
substantial direct reduction in air emissions.
5. Impacts On Existing Facilities
Specific concerns were raised during the legislative session that a
large wind facility in northern Maine, such as the Mars Hill project, could
have a detrimental impact on other generation facilities (particularly biomass
facilities). These concerns were driven
to some degree by the large size of the Mar Hills project (approximately 50 MW)
relative to the total northern Maine load (approximately 150 MW). The MPS system should not, however, be
viewed in isolation, but as part of the much bigger Maritimes control area.[47] There is currently 90 MW of available
transfer capability between MPS and New Brunswick,[48]
and MPS is planning to add additional transfer capability of 50 MW. There is currently 140 MW of generation
capacity on the MPS system. As a
result, a large amount of additional capacity beyond the Mars Hill project can
be added to the MPS system before there is any serious impact on the existing
biomass facilities in the area or on the development of additional generation
capacity.
In
the ISO-NE area of Maine, significant amounts of wind power development could
have some impact on existing facilities.
Maine is currently a large net exporter of power and the addition of
substantial amounts of any new generation in Maine could increase the amount of
time that there are transmission constraints in transferring power outside of
Maine. The result could be lower power
costs inside Maine (an outcome that would be desirable from the perspective of
Maine consumers), perhaps causing existing plants to operate in fewer hours or
possibly to shut down.[49]
In
addition, in either Maine area, it is possible that newly developed wind power
would be able to satisfy RPS requirements more economically than biomass
facilities and thereby affect their ability to remain viable. However, this is a function of the
competitive nature of RPS requirements that ultimately results in the
fulfillment of state renewable goals at the lowest cost to consumers.
VI. OBSTACLES TO WIND POWER DEVELOPMENT
Similar to most electric generation facilities, wind
power development faces a number of obstacles.
The primary obstacle to wind power development is the ability to obtain
long-term project financing.
A. Project
Financing and Long-Term Power Contracts
The most
substantial obstacle to wind development in this State (as well as elsewhere)
is the difficulty in obtaining project financing on reasonably attractive
terms. This difficulty stems from the
general lack of willingness of market participants to enter into long-term power
contracts. Financing entities are
generally reluctant to offer reasonable financing terms unless a project
developer has a long-term contract for power or for RECs. In this context, a long-term contract is in
the range of 10 to 20 years.
The current
reluctance of market participants to enter into long-term contracts is
attributable to several factors. One
major factor is the restructuring of electric industry on both the State and
regional levels. Industry restructuring
has resulted in the deregulation of many entities that are now responsible for
electricity supply. Unregulated
suppliers are less likely to enter into longer-term obligations with a
generation facility than regulated entities that have long-term load
obligations and for whom there is a greater certainty of cost recovery. In addition, restructuring has resulted in a
level of uncertainty about future market rules, creating further hesitancy to
make long-term commitments. Moreover,
the recent high-profile corporate scandals and the number of bankruptcies of
entities in the energy business have added to the perceived risk associated
with generating plant investment, increasing the difficulty in obtaining
financing. This situation is not specific
to wind power; all types of generation facilities face difficulty in obtaining
financing in the current market in the absence of long-term power
contracts. The general reluctance to
finance without long-term contracts could change as electricity markets become
more familiar to investors.
It is not
the case that project financing could never be obtained in the current market
without a long-term contract; however, the terms of such financing may often
render a project uneconomic.[50] Moreover, some entities are willing to enter
into longer-term contracts. Although
unregulated marketers will generally not contract for power for more than 5
years, traditional utilities with load obligations (such as Canadian utilities
and municipal utilities in some New England states) are willing to consider
longer-term power contracts.[51] Additionally, end-use customers, looking for
price stability over time, may also be willing to enter longer-term contracts.[52] Finally, some entities, primarily for
environmental reasons, may be willing to enter contracts to purchase RECs on a
long-term basis.
B. Public Opposition
Wind power
is generally viewed as environmentally benign relative to other generating
sources in that it produces no air emissions and thus does not contribute to
global climate change. As such, wind
generation has received growing support from environmental organizations
(although support of any particular project would depend on its location).
However, in many cases, public reaction can be among the most substantial
obstacles to wind development.
Depending on the particular site, public opposition to a wind project
can be severe and can be the major factor in its failure.
Public
opposition generally focuses on the potential for harm to migratory birds (and
other wildlife) and on visual impacts upon large areas of scenic
landscape. Current wind power towers
are higher than in the past and wind facilities cover a much larger area
relative to other types of generating facilities.[53] Thus, towers can often be seen from long
distances and are required to have lights that make them visible at night. Critics of wind power often argue that such
facilities take up extreme amounts of land for the amount of power they
generate, that they are noisy and dangerous in terms of ice build up, that they
have a negative impact on property values, that air emission benefits are often
significantly exaggerated, and that they are inefficient in that significant
back-up power is required.[54]
C. Environmental
Permitting
The
difficulty in siting wind power facilities around the country is sometimes
mentioned as a significant obstacle to development. However, wind power developers do not view the environmental
permitting process in Maine as unreasonable or unduly burdensome.
The process in Maine can be expected to take six
months to a year and the costs can vary.
For example, the permitting of the Mars Hill project has cost
approximately $300,000, while developers involved in the Redington project have
spent in the range of $2 million. Costs
in this range, although significant, do not comprise a large portion of total
project costs and would not therefore represent a barrier to wind development
in the State. Additionally, as more wind projects are permitted in Maine and
the standards and requirements become clearer, environmental impacts should
become better understood and the cost of permitting should come down.
The process in Maine is made somewhat more
complicated by the overlapping regulatory responsibilities of the Department of
Environmental Protection (“DEP”) and the Land Use Regulation Commission
(“LURC”). The DEP is the State’s
environmental agency, while the LURC has planning and zoning authority for the
State’s unorganized areas and plantations.
When a project is proposed to be located partially in LURC territory,
both DEP and LURC have environmental review responsibilities. The DEP must permit the whole project, while
LURC has authority only over that portion of the project that falls within its
territory. If the project is proposed
to be located entirely in unorganized territory, LURC conducts the
environmental review in conjunction with its rezoning authority (DEP conducts
the environmental review if rezoning is not required). If no portion of the project will be in the
unorganized territory, the DEP alone would conduct the environmental
review.
In situations of overlapping jurisdiction, the
agencies work closely to minimize developers’ filing requirements and maintain
consistent procedures. The agencies
have developed joint application checklists, hold joint application meetings,
and communicate regularly regarding projects under their joint review. In addition, discussion has occurred
regarding legislation that would remove the requirement for DEP to approve
projects in LURC territory provided that LURC is conducting such review. As wind projects become more prevalent,
direct experience should allow for continued process streamlining.
D. Grid Interconnection Procedures
The
process of interconnecting with the power grid is often mentioned as a barrier
to wind power development. The grid
interconnection process is somewhat complex, takes times and has a cost for
wind facilities.[55] However, project developers report that the
process in Maine to interconnect to the grid is not a barrier to wind power
development. In addition, the FERC has
recently opened a proceeding to review technical requirements for the
interconnection of large and small wind generators and to examine the need to
adopt specific interconnection standards for wind projects.[56]
E. Market Prices in Maine
As
a consequence of recently adopted regional market rules (referred to as
standard market design), wholesale market prices in Maine tend to be less than
prices in the remainder of New England.[57] This price impact is due to both
transmission constraints that limit the amount of power that can be exported
out of Maine at certain times of the year[58]
and the ISO-NE’s calculation of marginal line losses.[59] Although lower market prices are
advantageous from the perspective of Maine consumers, they are detrimental for
developers looking to locate a wind project in the State. However, wind facilities are not likely to
be required to shut down during times of transmission constraints because of
their low cost of operation (i.e. lack of fuel cost expense); during periods of
constraint, it is units with higher costs (and thus higher bids) that will not
be dispatched.
VII. SITING OF WIND POWER ON TRIBAL LANDS
Preliminary
evaluations reveal that there may be some realistic potential for wind power
development on tribal lands.
The Penobscot, Passamaquoddy, Maliseet, and Micmac
tribes are interested in exploring the potential for wind power development on
their tribal lands. Wind power
development may be particularly appropriate for tribal lands in that clean,
renewable power would be consistent with tribal values on the environment and
the use of natural resources.
Based on preliminary data, it appears that there is
a realistic potential for the development of significant amounts of wind power
on tribal lands.[60] The blueberry fields on Passamaquoddy lands
are high, open lands with substantial winds and a proximity to transmission
lines. These lands could potentially
support more than 100 MW of wind power. Preliminary information is also encouraging for wind development
on Penobscot lands. The Maliseet and
Micmac tribes are in earlier stages of considering wind power potential.
The development of wind power on tribal lands,
however, faces the same obstacles as development in other areas of the State.[61] As with any wind power project, the major
difficulty is obtaining long-term financing on reasonable terms. This problem is made more complicated in
that the applicability of state laws related to financing and contractual remedies
with respect to projects on tribal land is less clear than for other
projects. This creates some uncertainty
that could make financing more expensive or difficult to obtain. Ownership of facilities on tribal lands
appears to be a high priority for the tribes.
However, the tribes generally do not have the funds for large equity
investments. In addition, tribal
ownership could negate the benefit of the federal PTC because the tribal
projects are generally not taxable; a relatively large taxable corporation
would likely need to be involved as an equity owner for at least the 10-year
life of the PTC.
Section VIII of this report discusses the use of the
Finance Authority of Maine (“FAME”) as a means to aid in the financing of wind
projects more generally throughout the State.
The same considerations would apply to the use of FAME for tribal
projects. Any legislative decision to
authorize additional public or ratepayer support for FAME financed wind
projects would presumably also apply to tribal projects. Alternatively, the Legislature could choose
to make such additional FAME authority only applicable to projects on tribal
lands, thereby limiting FAME’s potential financial exposure.
The funding of studies necessary to determine the
viability of particular sites on tribal lands can also be a barrier to
development. The DOE has some programs
specifically for wind power development on tribal lands.[62] These programs can help provide the funds
necessary for pre-construction studies.
To the extent that support of wind power on tribal lands is a high
priority, the State can make funding available for pre-construction studies to
supplement those that may be available from the DOE. Such studies should cost in the range of $200,000 to $600,000 and
available funds (obtained from taxes or electric rates) could be distributed
through the State Energy Program (which is currently administered by the
Commission).
The requirements for environmental and land use
review on tribal lands may be a source of uncertainty for wind developers. While State environmental and land use
review processes apply on their face to tribal lands, the tribes have in the
past contested the extent of State jurisdiction. The confusion that may exist regarding environmental and land use
review for projects on tribal lands should dissipate to some degree when the
first tribal wind project completes a pre-construction review process.
VIII. ALTERNATIVE APPROACHES TO PROMOTING WIND POWER IN MAINE: CONSIDERATIONS AND RECOMMENDATIONS
To the extent that the promotion of wind power development is a substantial policy objective and the Legislature determines that some level of public support or subsidy is warranted, there are several viable mechanisms identified in this section of the report that could be implemented to promote wind generation. As a general matter, the Commission recommends the implementation of mechanisms that employ competitive processes to minimize the cost to Maine’s public. Moreover, any wind power promotion mechanism should be designed to carefully balance the costs and risks to taxpayers or ratepayers with the potential for public benefits. The precise determination of how such objectives could be achieved for each promotion mechanism would be a complex matter and are thus described only generally in this report. Finally, any seriously considered promotion mechanism should be examined to determine the applicability of federal law provisions that offset the amount of the federal PTC as a result of certain types of state incentives.
A. Renewable Portfolio Standard
1. General Description
A
renewable portfolio standard (“RPS”) was discussed at length during the last
legislative session as a mechanism to promote wind power development in Maine. Essentially, an RPS requires retail suppliers
of electricity to serve a specified percentage of their load in Maine through
designated categories of resources.[63] If appropriately designed, an RPS can be an
effective means to promote the development of desired resources that are not
yet commercially viable. However, a
properly designed RPS would come at some cost to electric consumers in that the
mechanism is a subsidy to the designated resources. The cost cannot be known in advance, but could be capped through
what is referred to as an “alternative compliance mechanism” (“ACM”) that provides suppliers with the
option of paying into a fund rather than meeting the portfolio requirement. Any money deposited into the fund would be
used to provide financial support to the designated renewable resources.
2. Appropriate Design
Several
variations of an RPS that would promote wind development were discussed during
the last legislative session. In
addition, the Commission proposed a mechanism in its recent report on the
promotion of renewable power.[64] All the mechanisms were similar in design,
one that is common in other states (e.g. Massachusetts and Connecticut). The approach would be to establish a
separate RPS category for particular types of renewables (e.g., new, wind,
low-impact hydro). The category could
include wind power as one of the resources that would be likely to be used by
suppliers to meet the requirement.[65] The percentage requirement would start out
small (e.g. 1.0% or 2.0%) and grow by a specified amount for a fixed period of
time (e.g. 0.5% or 1.0% each year) until a designated percentage is reached
(e.g. 5%). An ACM was included in all
of the RPS proposals that ranged from the Commission proposal of 2.5˘/kWh to
ACMs approaching 5˘/kWh. For reference,
a 2.0% portfolio requirement with a 5˘/kWh ACM would cap electric consumer cost
exposure at approximately $11 million for a one-year period, or approximately
0.1˘/kWh if applied across all kilowatt-hours sold within the State.
3. Mitigation of RPS Costs
The
major concern with an RPS is its cost to electric consumers. As mentioned above, an effective RPS is
essentially a subsidy and should be implemented to promote resources that are
desirable from a public policy perspective, but not yet commercially viable (an
RPS can be phased out once the targeted resources become commercially
viable). As the cost of eligible
resources approach market prices, the cost of an RPS to consumers should approach
zero (assuming that the RPS works correctly). [66] Because the
cost of wind power is approaching market prices, the cost to consumers can be
expected to be relatively low over time.
However, in the near term, due to the demand for wind power created by
the Massachusetts and Connecticut RPSs (and those in other states in the
region),[67] the cost to
Maine consumers is likely to approach the ACM.
There
are mechanisms that can be used to “mitigate” the costs to consumers of an RPS,
each of which was discussed during the legislative session. Because an RPS is a means to subsidize
specified resources, there will generally be some cost to consumers. Possible “mitigation” mechanisms are:
ACM: The primary mechanism
to mitigate the cost to consumers of an RPS is an ACM. This mechanism serves as a cap on consumer
cost exposure so that the Legislature can decide in advance the maximum amount
of subsidy it desires to authorize.
Consumer payback: Another
mechanism that could serve to lower the cost of an RPS would be the inclusion
of a “consumer payback” provision. An
RPS acts to provide a subsidy to resources at time of relatively low market
prices. If market prices rise high
enough for a sustained period of time, the subsidy should be reduced to zero
and the resource could become very profitable.
A customer payback mechanism would provide for some sharing of the
resource’s high profits for the benefit of consumers under these types of
circumstances.[68]
4. Considerations
An
RPS can be an effective means to promote a particular resource. However, an RPS does not appear necessary to
promote wind power development in Maine at the current time. The RPSs in
Massachusetts and Connecticut are having the impact of stimulating wind power
development in Maine and can be expected to do so into the foreseeable future
(the recent adoption of RPSs in other states in the region may have a similar
effect). However, eventually, wind
power facilities (and other qualifying resources) will develop and the supply
will tend to correspond with the demand created by the regional RPS. In such a case, a revised Maine RPS would
stimulate more wind development than would otherwise occur; however, there is
no way to know in advance how much of that development would be located in
Maine nor what the modified RPS would ultimately cost ratepayers. Conversely, to the extent that eligible
generation becomes competitive with other sources of generation and, therefore,
naturally enters the system mix, the cost to electricity consumers is
inherently decreased. Moreover, an RPS
does reflect the benefits of a competitive process as each supplier has the
incentive to minimize their costs while meeting their obligations.
Notwithstanding
the above, as discussed in section VI of this report, the major barrier to wind
power development is the difficulty in obtaining project financing, which is
related to the general hesitancy of market participants to enter into long-term
contracts for power. The adoption of a
revised Maine RPS is not likely to have a direct or significant impact on the
willingness of market participants to enter into long-term contracts. Legislative action regarding an RPS can be
changed by any future Legislature and thus the necessary certainty is not
likely to exist to overcome the risk aversion that is currently preventing
market participants, as a general matter, from making long-term
commitments. A revised Maine RPS, along
with the existence of RPSs in most states in the region, may have some
incremental effect in contributing to a change in attitude regarding long-term
commitments over time.[69]
5. Recommendations
To
the extent that the Legislature decides to promote wind power development both
within the State and the region through some level of public subsidy, the
Commission recommends adoption of a revised Maine RPS. The design should be similar to that
discussed during the last session: a small percentage portfolio requirement for
certain renewables that grows gradually over time and is capped by an ACM. By itself, a revised RPS would do little in
the short-term to encourage new renewable development (it is likely that a
significant portion of the requirement would be met through the ACM). However, it would signal the State’s
commitment to wind power and would assure that Maine does its share to promote
regional wind development over the long-term, rather than relying on the
actions of other states. The Commission
does not consider the adoption of a revised RPS to be an effective means of
addressing the long-term financing problem, at least not in the shorter term.
B. System Benefit Charge
1. General Description
A
system benefit charge (“SBC”) is a commonly used mechanism to support renewable
resources. The mechanism is a surcharge
on the bills of T&D utility customers.
The funds are collected and distributed to support specified resources
according to previously established criteria.
By its nature, an SBC is a subsidy that results in a direct increase in
T&D utility rates for electricity consumers.[70]
2. Considerations
An
SBC can be an effective mechanism to promote larger grid-scale wind facilities,
as well smaller on-site applications and community wind projects.[71] An SBC can be designed so that only
facilities in Maine benefit through the receipt of funds and may be able to
provide some aid in obtaining project financing through a long-term commitment
for assistance. Additionally, an SBC can be structured to aid wind development
through the purchase of RECs or the guarantee of REC prices. [72] An SBC can be structured to cap the cost to
ratepayers. An SBC does require
significant resources to administer.
3. Recommendations
In
the event the Legislature determines that larger scale wind power development
is a substantial public policy and should be promoted through use of
electricity consumer funds, the Commission recommends the adoption of a revised
Maine RPS as an efficient, market driven mechanism for the promotion of
resources. However, an SBC can also be
structured to be effective in promoting larger scale facilities. If the Legislature adopts such a mechanism,
the Commission recommends that the SBC be designed so that projects are chosen
based on a competitive auction and ratepayers are compensated if markets prices
or project profits reach certain levels.
If the policy goal is to promote smaller scale, on-site wind power
applications through the use of electricity consumer funds, the Commission
recommends the adoption of an SBC. A specific recommendation for an SBC was
included in the Commission’s recent report to the Legislature on the promotion
of renewable power. [73]
C. FAME Financing
1. General Description
The
basic mission of the Finance Authority of Maine is to facilitate access to
capital for business projects that would have difficulty accessing the private
capital market and are considered to be in the public interest. FAME generally assists in project financing
by providing credit assurances backed by its cash reserves and the moral
obligation of the State; private lenders actually make the loan. Thus, if a project is too risky, private
financing could not be arranged even with FAME backing. On some occasions, FAME lends money directly
to business projects.
As
a general matter, FAME is willing to accept a higher level of risk than private
lenders. However, a private lender must
be found to make the loan. The amount
of FAME credit assurances for individual projects is limited by its amount of
reserves. By statute, the maximum
amount of credit assurance per project is $7 million, but FAME’s internal
policies result in a practical maximum closer to $5 million per project.[74] Under its current statutory authority, FAME
can provide credit assurance for electric generation projects,[75]
such as wind power facilities, consistent with its normal review procedures and
funding limits.
2. Considerations
As
discussed in section VI of this report, the difficulty in obtaining long-term
financing on reasonable terms is the largest barrier to wind development in the
State. Moreover, because wind projects
are so capital intensive, a small change in the finance rate can have a
substantial impact on a project’s economics.
Thus, it is logical to consider the potential for FAME to aid in
development of wind facilities. FAME’s
participation could be especially important if the difficulty in obtaining wind
project financing were due to an exaggerated nervousness of the capital markets
regarding the restructured electricity markets (especially in the wake of the
Enron scandal and other bankruptcies of energy trading companies) and a general
lack of familiarity of lenders with wind technology. If this is the case and the encouragement of wind power
development in the State is considered a substantial public policy goal, then
FAME financing of wind projects would appear appropriate. However, major wind projects such as Mars
Hill and Redington have a project cost in excess of $50 million and, assuming a
50% equity investment, a debt financing requirement of more than $25
million. This is significantly beyond
FAME’s statutory and practical financing limits.
In
the event the Legislature determines that wind development is a substantial
public policy goal, it can so inform FAME and provide FAME with specific
direction to consider wind projects.
This would encourage the financing of smaller wind projects, consistent
with FAME’s current capacity and standards of review. Larger projects would not be aided by such a pronouncement unless
the Legislature acted to increase FAME’s financial resources in some
manner.
Additional financial resources could be obtained
from either public or ratepayer dollars.
If the Legislature chose ratepayer dollars as the funding mechanism, the
conservation program fund (established pursuant to 35-A M.R.A. § 3211-A) would
be a possible source. However, the
conservation fund generates in the range of $15 million per year of which
approximately half is already committed by contract. This does not leave sufficient funds over the next several years
to finance even one major wind project.
In addition, any funds diverted from the conservation fund to support
wind power projects would leave significantly less support for the intended
purpose of encouraging energy efficiency and conservation. This could hamper the efforts of Efficiency Maine, which already does not have
enough funds to pursue many of the cost-effective efficiency measures that
exist in the State.
An
alternative to using Efficiency Maine funds would be for the Legislature to
guarantee through specific statements in the law that ratepayers will be an
additional source of income if there is a default on a FAME-backed loan. This has the advantage of encouraging wind
power development in a manner that would have no cost for projects that do not
default on their financial obligations.
There could be significant costs if a FAME-backed project did default on
its obligations, although it may be possible to recoup some of these costs
through a sale of the facility or by the assumption and sale of the
output. The Commission could be charged
with aiding FAME in its analysis of the financial viability of projects.
Another
approach is for the Legislature to direct FAME to administer a program whereby
the combined price of energy and RECs is guaranteed through ratepayer funds.[76] Fulfillment of such a guarantee would not be
triggered and no ratepayer cost incurred unless the combined price fell below a
pre-specified amount. A mechanism could
also be included that would have a percentage of revenues paid to the benefit of
ratepayers if the combined price rose above a specified amount. As with a loan guarantee program, the
Commission could be directed to aid FAME in its effort to administer a price
guarantee program.
Finally,
FAME can act to insure a relatively small portion of the debt financing (e.g.
$4 million out of a $25 million loan).
In some cases, the provision of such insurance can be enough for
borrowers of relatively less risk to obtain financing. FAME can act in this regard under its
existing authority.
3. Recommendations
The
Commission recommends that FAME be considered as a means to address the
long-term financing issues involved in wind power development if appropriate
legislative findings are made. Any
decision to provide FAME with additional direction or funding to support wind
power development in Maine should be based on a clear legislative finding that
such development is not only of substantial public interest, but also worthy of
public funding. If so, it would not be
inappropriate for ratepayers, as the ultimate users of electricity, to be the
source of the public funding.[77] If the Legislature makes the appropriate
findings, the Commission recommends that consideration be given to using
ratepayer funds as the backup for both loans and price guarantees as described
above.
D. Tax
Incentives
1. General Description
A
common means for states to offer
financial incentives for the development of wind power is through tax
incentives of some type. Approximately
half of the states provide corporate tax incentives or sales tax exemptions as
means to support wind power.[78] One approach to providing tax incentives for
wind power development in Maine would be to designate all wind facilities as
qualified Pine Tree Zone businesses regardless of their location and their
status as a manufacturing operation.[79] This would provide wind developers with
significant breaks on corporate income tax, as well as other benefits. Another approach would be a reduction in
property taxes that would tend to reduce the burden on wind farms on a
kilowatt-hour basis relative to natural gas facilities.
2. Considerations
Wind
power development already receives substantial tax incentives from the federal
government. As discussed in section III
of this report, wind projects continue to receive significant federal
production tax credits and are entitled to 5-year accelerated
depreciation. As a consequence, further
tax incentives or subsidies are not necessary for larger scale wind projects to
be
viable in the New England electricity market. However, tax incentives could be meaningful in promoting smaller
on-site or community wind projects.[80]
As
discussed in section VI of this report, the primary barrier to larger-scale
wind power development is the difficulty in obtaining project financing, which
is tied to the reluctance of market participants to enter long-term power
contracts. Tax incentives will lower
the cost of the project and could be beneficial to project financing; however,
in the absence of a long-term power contract, they are not likely to make a
significant difference in the receipt of financing.
3. Recommendations
In
the event the Legislature determines that grid scale wind power should be
promoted through some type of public funding, the Commission recommends against
using state tax incentives, including expansion of the Pine Tree Zone
eligibility criteria. An RPS provides
an efficient, market-based mechanism to encourage a category of generating
resources. Moreover, a program to encourage
wind power financing through FAME would be the most direct means to address the
primary obstacle to wind power development.
Accordingly, the Legislature should prefer those mechanisms over tax
incentives. For the promotion of
smaller on-site or community wind projects however, the Commission recommends
consideration of tax incentives as an appropriate support mechanism.
E. State
or State-Mandated Purchases
1. General Description
Another approach to promote wind power development
is for the State to directly enter into long-term purchase contracts for the
output from wind facilities or by mandating that utilities or standard offer
providers enter into such long-term purchase arrangements.[81] One alternative would be for the State to
purchase power from wind facilities for its own needs or on behalf of the
State’s electricity consumers. The
other alternative would be for the State to mandate by law that utilities or
standard offer providers purchase wind power and either sell the output into
the regional wholesale market or use the output to serve Maine consumers.
2. Considerations
The
existence of State or State-mandated long-term purchase obligations (e.g. 10 to
15 years) should greatly facilitate project financing. As discussed in section VI of this report,
the availability of project financing is the major barrier for wind power
development and the difficulty in obtaining long-term power purchase contracts
is the greatest obstacle in achieving project financing.
The
State already purchases a portion of its retail electricity needs from green
marketers under relatively short-term contracts. The State could modify this
program by entering into longer-term arrangements for retail service from a
wind facility. Such arrangements could
serve as a hedge against price volatility and result in overall lower prices,
but might also lead to significantly higher retail electricity rates for State
facilities than would have otherwise occurred.
The arrangements would be complicated by the need for a retail
electricity supplier to incorporate the wind power into an all-requirement
service for the State. The combined
load of State facilities would appear large enough to make some difference in
the development of wind projects.
A
long-term purchase directly by the State on behalf of electricity consumers
would be problematic, because the State is not a participant in the regional
market. Since utilities and standard
offer providers are market participants, it would be more practical to require
them to purchase power from wind facilities that would either be resold into
the market or used to serve retail consumers.
A long-term
power purchase obligation might serve as protection against market volatility,
but would also place Maine’s electricity consumers at risk for paying
substantial above-market rates depending on market conditions. Such an approach
would also move in the opposite direction from that contemplated by industry
restructuring in that electricity consumers would again be subject to resource
acquisition risks that could translate into new stranded costs.[82] At the direction of the Legislature, the
Commission has conducted a rulemaking proceeding to adopt standards and
procedures for the incorporation of new renewable resources into standard offer
supply as a hedge against price volatility.
As required by law, the rule will allow the Commission to require the
use of power from new renewable facilities for standard offer supply, but only
when doing so would provide an effective hedge against price volatility while
maintaining a competitively-priced standard offer. The adopted rule will be subject to legislative review and
modification.[83]
3. Recommendations
The
Commission has no recommendation on whether the State should enter into
long-term purchases of wind power for its own retail purposes. However, it is reasonable for the State to
investigate this option by considering the price impact on Maine’s taxpayers
and recommendations of the DEP in its Climate Action Plan.
The
Commission does not recommend that any additional purchase obligations be
imposed beyond that which might be incorporated into the legislatively approved
standard offer hedging rule. Beyond
the use of new renewable resources as an economic hedge against price
volatility, long-term purchase requirements represent a consumer subsidy that
cannot be known in advance and is not targeted to minimize public costs. It is preferable to use a promotional method
under which the potential cost to customers is known in advance. In addition, long-term purchase requirements
are contrary to a primary goal of electric industry restructuring, which was to
transfer the market risks of long-term resource acquisitions away from ratepayers. In the event the Legislature decides to
require state-mandated purchases of wind power, the Commission recommends the
use of a competitive auction for the desired amount of capacity so as to
minimize the cost to electricity consumers.
F. Environmental Permitting
1. General Description
As
discussed in section VI of this report, under the current regulatory structure,
both the DEP and LURC have environmental review authority depending on the
location of the project and both can have environmental review authority over
the same project. The DEP and LURC have
different review procedures and standards for project approval. Currently, both the DEP and LURC have
general review procedures and standards, but neither agency has specific
procedures for reviewing wind projects.
2. Considerations
The
DEP is the State’s environmental review agency. LURC does not have the same type of expertise or the resources of
the DEP to conduct environmental reviews, but does seek technical assistance
from DEP (and other agencies) for certain aspects of a development
project. Because two agencies (with
different procedures and standards) have environmental review responsibilities
depending on project location, the current regulatory structure appears to have
the potential for inconsistent application of environmental policy and
inconsistent results across the State.
In addition, although the DEP and LURC have made substantial efforts to
coordinate and streamline their processes when environmental review of the same
project is required by both agencies, developers must interact with and become
familiar with the processes of two agencies.[84]
By
law, the DEP reviews projects to determine whether they would have an
unreasonable adverse impact according to statutory criteria. Thus, the DEP considers the severity of the
impact a project would have on the environment and means to mitigate that
impact. The DEP is not permitted to
balance adverse environmental impacts against any resulting environmental benefit. Consequently, the DEP cannot consider the
environmental benefit associated with wind facilities in reducing air emissions
as part of the permitting process to offset an adverse impact. LURC appears to have the flexibility to
consider environmental benefits through its requirement to assess the “need”
for the project.
Neither
the DEP nor LURC have specific regulations regarding the permitting of wind
facilities. A number of states do have
specific filing requirements for wind projects.
As
discussed in this report, the suitability of a particular area within the State
for wind development is often likely to be a matter of significant
controversy. One approach would be to
pre-define those areas of the State in which wind power development would
either be appropriate or inappropriate from an environmental impact
perspective. Such an approach would
likely involve significant resources to review sites for which wind developers
may never be interested. Another
approach would be to provide guidance to developers through a pre-established
list of criteria and standards.
3. Recommendations
The Commission recommends that the Legislature discuss with the DEP and LURC the merits of the current regulatory scheme and alternatives that may provide for an improved approach to environmental permitting (while LURC maintains its land use jurisdiction over the unorganized territories).[85] Although the DEP and LURC do act to coordinate their processes, there may be approaches (such as placing all environmental review authority within the DEP or removing the circumstances in which both the DEP and LURC would conduct an environmental review over the same aspects of a project)[86] that could create efficiencies, avoid duplication of effort among state agencies, and make the environmental permitting process more consistent for wind developers.
The
Commission recommends that consideration be given to explicitly modifying the
DEP’s review standard to allow the agency to consider environmental benefits of
wind facilities as part of the permitting process. In particular, amendments should be considered that would allow
the environmental review process to take into account the benefits of reduced
air emissions.
The
Commission does not recommend that separate regulations or application
processes be adopted for wind power at this early stage of the industry’s
development. The adoption of separate
regulations could be controversial, take a significant amount of time, and
cause project review delays. Although
the regulations are very general in nature, the current the DEP and LURC
processes are quite flexible, involving a number of pre-application meetings to
determine in advance the information and studies that would be necessary to
support an application for a permit.[87]
The
Commission does not view an effort to pre-identify areas of the State as
environmentally appropriate or inappropriate for wind development as likely to
be fruitful. Any effort to pre-identify
environmentally appropriate areas that also have the necessary wind resource
and infrastructure would be difficult, take a large amount of time, and be
controversial. It should be the task of
project developers, at least in the first instance, to consider individual
sites for their feasibility for wind development. Additionally, pre-identifying sites would likely remove certain
areas from consideration, while not significantly reducing controversy
regarding projects proposed for the pre-identified areas. Finally, as wind power technology changes, different
type of sites may become feasible for wind development and this might require
periodic updates of the appropriate and inappropriate areas. However, the Commission considers efforts of
appropriate agencies to provide non-site specific guidelines and standards
regarding wind power development as holding substantial potential in creating a
higher degree of predictability with respect to agency decisions.
G. Public Acceptance
1. General Description
As
discussed in section VI of this report, public opposition can be one of the
major barriers to wind development.
Public opposition generally centers around the impact a project will
have on the aesthetics of the view or on harm to migratory birds. However, opponents also cite exaggerated air
quality benefits, decreased property values, noise, icing issues and light
flicker as problems with wind power development.
2. Considerations
There
has been no major wind power development in the State or the region, arguably
due in part to public opposition. Some
public reaction may result from a lack of familiarity with wind power. In addition, the public may not be fully
aware of the damage caused by emissions from the current mix of fossil-fuel
generation in the region and the potential for wind power to reduce that
damage. A campaign aimed at promoting
the benefits of wind power could help modify public perception and reduce
opposition.
3. Recommendation
During
its last session, the Legislature adopted a requirement that the Commission
inform consumers of the benefits of renewable power and the opportunities
available to purchase electricity generated by renewable resources.[88] The statute specifies that the Commission
may not promote any particular renewable resources over others. In the event that the Legislature determines
that the promotion of wind development in the State is a high priority, it can
amend the law and give the Commission direction to educate the public
specifically regarding the benefits of wind power.
IX. CONCLUSION
Whether the State
should actively promote wind power as part of its overall energy policy, or
should spend public or ratepayer funds to aid wind power development in Maine,
are fundamentally legislative questions.
This report identifies some environmental and system diversity benefits,
as well as other considerations, upon which the Legislature may make policy
determinations regarding wind power development. There is substantial potential for wind power development in the
State, including development on tribal lands, and sufficient markets exist in
the region for the sale of electricity from Maine wind power facilities. Wind power development in reasonable likely
amounts does not present any serious or insurmountable system reliability or
market operation concerns. The cost of
wind power is currently competitive with other generating resources in the
region, assuming the continuation of federal tax incentives, and larger scale
wind projects do not require further financial assistance or subsidies to allow
them to compete on a cost basis. The
primary obstacle to wind power development, as with other generating
facilities, is the difficulty in obtaining project financing on reasonable
terms. There are several viable
mechanisms that could be implemented to promote wind power development if the
State makes the appropriate policy determinations.
[1] Entities
with whom the Commission held discussions are listed in Appendix A of this
report.
[2] Written comments on the draft report can be
viewed at www.state.me.us/mpuc by
going to the virtual docket and referencing Docket No. 2004-810.
[3] The
Pacific Northwest Laboratory (“PNL”) developed these Classes in the late 1970s
and they are still widely quoted in the industry. Wind power density is a better measure of the energy potential
from a wind location than is wind speed, but it is complex to calculate and to
understand. Thus, many maps consider
only wind speed. A description of the
PNL classes is contained in Appendix B to this report.
[4] Very
large projects could likely support greater distances of transmission
construction.
[5] Although
wind speed generally increases with elevation, mountain ridges above certain
altitudes (generally around 4,000 ft) are not good candidates for development
because of harsh weather and the potential for ice build up.
[6] Such maps
of northeastern states have been produced by TrueWind Solutions of Albany, NY.
[7] A
regional wind map at 70 meters is contained in Appendix C to this report. Maps at additional heights and an interactive
map allowing investigation of particular geographic areas may be found at
http://www.mtpc.org/RenewableEnergy/green_power/wind_energy.htm.
[8] A table
with the PNL results is contained in Appendix D to this report.
[9] A table
with the NREL results is contained in Appendix E to this report.
[10] Maine’s
Climate Action Plan stakeholders used the Connecticut group results as an input
for computer modeling whose results indicated very little wind potential in
Maine (in the range of 30 MW under the reference case). The stakeholders agreed that this was an
unreasonably low estimate. The
Commission also agrees that this conclusion is not reasonable given the known
level of interest in developing wind generation in Maine.
[11] The
realization of the State’s wind potential as described in this section of the
report would require the installation of hundreds of large wind towers in
various areas around the State. For
example, 1000 MW of wind capacity would require over 650 wind turbines,
assuming each turbine had a capacity of 1.5 MW.
[12] There are
smaller scale facilities used primarily to serve on-site needs. For example, G.M. Allen & Sons, Inc.,
which owns and operates a blueberry processing facility in Orland Maine, makes
use of a 50 kW wind power project located on its premises.
[13] There are
several smaller facilities in operation in New England. These include facilities located in
Princeton, Massachusetts (0.3 MW), Searsburg, Vermont (6 MW), and Hull,
Massachusetts (0.7 MW). The Hoosac Wind
project in Massachusetts has permits to expand from 6 MW that are currently
operational to 40 MW. A large facility,
known as Cape Wind (420 MW), is being considered for waters off of Cape Cod; it
would be the first offshore wind facility in the United States.
[14] Exporting
power would likely require a statutory change because current law prohibits
consumer-owned utilities from providing wholesale generation service except for
“incidental sales.” 35-A M.R.S.A. §
3207(1)(B).
[15] The costs
in this section refer to the all-in, average life cycle cost of generation
(both capital and operating costs).
This section does not discuss “indirect costs” such as the cost of
additional system reserves or transmission upgrades, nor does it discuss any
potential cost benefits such as cost reductions that may result from greater
fuel diversity (these are discussed in section V of this report).
[16] The PTC
is applicable for the first 10 years of a facility’s operation. Federal tax code provisions for accelerated
depreciation also help the commercial viability of wind power.
[17] Capital costs are assumed to be $1,200 per kW, the debt-equity ratio is assumed to be 50/50, the capacity factor is assumed to be 31%, the return on equity is assumed to be 12%, the realized effect of the PTC is assumed to be 1.6 ˘/kWh and the project is assumed to be amortized over 15 years. This example is intended only to provide a general representation of wind generation costs under a simplified set of assumptions. It does not include the effect of taxes or the time-value of money as these factors can vary significantly depending on the specifics of a project and a project’s financing structure. In addition, this table reflects the PTC as it would exist for the first 10 years of the project, not averaged over the life of the project.
[18] A
significant amount of literature suggests that the capital cost of grid scale
wind facilities is in the range of $1,000 per kW. If this capital cost is assumed (along with the other cost
assumptions stated above), the cost of wind power drops to between 5 and 6˘/kWh
without the PTC and between 3 and 4˘/kWh with the PTC.
[19] The cost
of debt likely varies significantly among developers. A private developer will likely pay at least 8% debt. However, if a generator is financed on the
balance sheet of a large electric utility or generation owner, as has been the
case for the majority of generators built in recent years, the debt payment may
be closer to the overall corporate debt rate, which is likely to be lower
because of project diversity.
[20] On a per
kilowatt-hour basis, property tax constitutes four times the cost of wind power
compared to a gas facility because wind facilities cost more to build and have
lower capacity factors.
[21] The
American Wind Energy Association has stated that an increase in average wind
speed of 2 miles per hour could result in the generation of 50% more
electricity.
[22] To
illustrate the sensitivity of wind power costs to capacity factor, if a 25%
capacity factor is assumed in the cost example presented above (rather than the
31% capacity factor assumption), the cost of wind power would be between 7 and
8˘/kWh without the PTC and 6 and 7˘/kWh with the PTC.
[23] The
federal PTC expired during 2003 and its renewal was unknown through most of
2004. The Congress recently extended
the PTC though 2005. The American Wind
Energy Association has stated that the PTC is a critical factor in financing
new wind power facilities.
[24] Southern
Maine comprises approximately 10% of ISO-NE’s load and northern Maine comprises
approximately 3% of the Maritime’s load.
[25] The PJM
control area consists of Pennsylvania, New Jersey, Delaware and Maryland.
[26] The
Maritimes control area includes New Brunswick, Nova Scotia, Prince Edward
Island and northern Maine.
[27] The
details of the RPS in Massachusetts and Connecticut are included in the
Commission’s recent report to the Legislature on the promotion of renewable
resources. Report and
Recommendations on the Promotion of Renewable Resources, pages 57-60 (Dec.
31, 2003) (“MPUC Renewable Report”).
[28] The
tariffed transmission costs to transmit power out of northern Maine, through
New Brunswick and down to the NEPOOL system range above 2˘/kWh. However, in some circumstances, it may be
possible to obtain discounts off the tariffed rates.
[29] In addition,
the MEPCO line that connects the New Brunswick system to the NEPOOL system is
currently fully subscribed for firm capacity.
It is unclear, however, whether this is likely to present a significant
obstacle for wind developers as non-firm capacity is often available. Moreover, a second tie-line, if constructed,
would provide additional capacity for transactions from northern Maine into the
ISO-NE control area.
[30]
Connecticut requires the resource to be located in the ISO-NE control area or
in neighboring states with comparable renewable requirements, including
northern Maine.
[31] New
Jersey and Maryland also have recently adopted or revised RPSs in which Maine
wind facilities would be eligible subject to deliverability requirements. The cost of delivery, however, may be
economically prohibitive.
[32] As a
result of a recent ISO-NE ruling, the cost of the second tie-line will be
rolled into the regional transmission tariff and will therefore not represent a
cost to generators that transport power on the line. The tie-line requires the approval of the Commission and a permit
from the DEP. All necessary approvals
on the Canadian side of the border have been obtained.
[33] For
example, in Maine, over a thousand residential customers purchase power from a
green supplier and the College of the Atlantic, Colby College, Bangor
Theological Seminary and Unity College have decided to make a commitment to
green power. The State has about 750
accounts (approximately 10% of its load) that are served by a green
supplier. Green power products that are
available in Maine can be found at the Maine Green Power Connection website,
www.mainegreenpower.org.
[34] P.L.
2003, ch. 665, sec. 1.
[35] Wind power development in Europe
has generally been subsidized to varying degrees.
[36] The
Effects of Integrating Wind Power on Transmission System Planning, Reliability,
and Operations, Commissioned by the New York State System Operator and the
New York State Energy Research and Development Authority (Feb. 2004).
[37] The
impact of wind power development on reserves depends on the characteristics of
the particular system. For example, one
study has concluded that a 10% penetration of wind power in Minnesota will
increase the cost of reserve power.
However, because of the wind patterns in Minnesota, the system must be
able to compensate for the loss of all wind power. The situation would be different for a number of wind facilities
scattered around New England.
[38] Because
tripping off line during low voltage can cause significant system problems as the
number of wind facilities increases in New England, the ISO-NE has recently
decided to require all wind facilities to have the capability to remain on line
in the event of a voltage drop.
[39] The cost
of such equipment additions is borne by the wind project developers.
[40] Vars are
essential to stabilize voltage at a level required to move power across the
grid. The electric grid needs a
specific level of reactive power voltage—too much or too little can shut down
transmission lines.
[41] FERC is
currently considering whether transmission service should be reformed to better
accommodate intermittent resources and whether current market rules unduly
penalize intermittent resources. FERC
Docket No. AD04-13.
[42]
Consistent with its statutory obligations to work on the regional level to
promote the generation of electricity from renewable resources when the
interests of consumers are not adversely affected, 35-A M.R.S.A. § 3302(3), the
Commission will act to encourage the ISO-NE and the northern Maine ISA to
develop market rules that take into account the characteristics of wind power
and that are fair to all market participants.
[43] The
ISO-NE would generally assign a wind facility a capacity value of 25% of the
facility’s total capacity. This amount
could change depending on the actual operation of the facility.
[44] However,
a recent study by the New York State Public Service Commission found that
although most ratepayers would experience modest bill increases due to the New
York RPS, some ratepayers may experience bill decreases from the suppression
effect on supply and capacity costs in particular locations. New York Renewable Portfolio Standard
Cost Study Report II, New York Department of Public Service (Feb. 2004).
[45] For these
types of reasons, the ISO-NE has expressed the need to consider alternative
energy sources such as wind. In
addition, a U.S. Department of Energy white paper states concerns about the
ability of the natural gas industry to meet current requirements in New England
and concludes that diversification through use of renewable resources in the
region would improve reliability and lower energy costs.
[46] Based on
the “2002 NEPOOL Marginal Emission Rate Analysis” conducted by the ISO New
England, each megawatt-hour of wind generation would directly avoid 1,338
pounds of CO2, 3.3 pounds of SO2 and 1.12 pounds of
NOx.
[47] The total
generation capacity in the Maritimes control area is in the range of 6000
MW.
[48] The total
transfer capability is 200 MW, but only 90 MW is available on a firm basis.
[49] The issue
of transmission constraints and the impact on market prices in Maine is
discussed further in section VI of this report.
[50] A study
done in the 1990s by NREL estimated that wind generators’ cost of debt may
translate into increased costs of 1.3˘/kWh compared to a gas plant’s cost of
debt. Currently, wind power facilities
are likely to face financing rates that approach those of other generating
facilities.
[51] The Daily
FERC reported in December 2004 that a group of municipal utilities in
Massachusetts agreed to purchase 15 MW of wind power under a 22 year contract
for a fixed price of 3.65˘/kWh.
[52] An
end-use contract for wind power would be complicated by the need for power from
other sources when the wind resource is not available.
[53] The
towers of the latest wind facilities are in the range of 200 to 300 feet and
the blades are 100 to 150 feet long.
[54] Many of
the specific characteristics of wind power are discussed throughout this
report. However, as stated in section
I, the Commission’s charge is not to evaluate the variety of claims regarding
wind power or to make a judgment regarding whether State government energy
policy should include support of wind power.
With respect to the major grounds for public opposition discussed in
this report, the State’s environmental, land use, and other applicable agencies
are better equipped to consider arguments and make the appropriate
judgments.
[55] For
example, generation project developers are required to pay for the cost of
system impact studies.
[56] In the
context of a proceeding to assess the state of wind energy in wholesale
markets, the FERC issued a briefing paper that discusses many of the same
issues included in this report. The
briefing paper is available at http://www.ferc.gov/EventCalendar/Files/20041122142848-ad04-13.pdf.
[57]
Generally, market prices in Maine tend to be 0.5˘/kWh less than the rest of New
England.
[58] There is
currently 2,000 MW of transfer capacity between Maine and New Hampshire and 700
MW of transfer capability between the ISO-NE portion of Maine and New
Brunswick.
[59] The line
loss calculation is responsible for approximately two-thirds of the price
differential; as a result, removal of the transmission constraints would not
equalize prices with the rest of New England.
[60] Appendix
F to this report shows the locations of tribal lands. When compared to the wind maps in Appendix C, it can be seen that
wind density is fairly high on some portions of tribal lands.
[61] Obstacles
to wind power development are discussed in section VI of this report.
[62] For
example, the DOE has an anemometer loan program.
[63] For a
detailed discussion of RPSs, their operation and implications, see MPUC
Renewable Report at 21-23.
[64] MPUC
Renewables Report at 62-67.
[65] The other
renewables that were discussed include solar, tidal, wave, geothermal, landfill
gas, and fuel cells.
[66] An RPS is
designed to use competitive forces to drive prices down towards costs. The existence of any type of market power
could frustrate this outcome.
[67] As
discussed in section IV of this report, the demand created by RPSs in other
regional states is likely to be significantly greater than the available supply
for several years.
[68] The
concept of consumer payback mechanisms is discussed in the MPUC Renewables
Report at 19-20.
[69] The reasons for the current hesitancy regarding
long-term commitments are discussed in section VI of this report. As the regional market (and associated
market rules) become more stable and the likelihood of state and federal
policies remaining in place increases, the general reluctance regarding
long-term commitments may decrease.
[70] An SBC is
the mechanism currently used in Maine to fund energy efficiency programs and
support for low-income electricity consumers.
The mechanism, its operation and implications are discussed in detail in
the MPUC Renewables Report at 23-25.
[71] Community
wind projects refer to small projects (generally less than 2 MW) owned by local
landowners or municipalities.
Massachusetts uses funds from its SBC to provide pre-development and
development services for such projects.
[72] For
example, the Massachusetts Renewable Energy Trust Fund, which is supported
through a SBC, has entered longer-term contracts (e.g. for years 6 through 15
of operation) for the purchase or guarantee of REC prices so as to support wind
power development. Funds to support
such contracts are put into escrow as assurance to those financing the
facility.
[73] MPUC
Renewables Report at 67-70.
[74] Under
specific statutory provisions, 35-A M.R.S.A. § 3156, 10 M.R.S.A. § 1053(6),
FAME can finance much larger amounts for the purposes of utility buyouts or
restructurings of qualifying facility contracts. The ability to finance large amounts for such purposes results
from the utility loan being backed by a ratepayer-funded revenue stream
specifically authorized by the Legislature and the Commission.
[75] For
example, within the past year, FAME has backed the refurbishing of biomass
plants in Maine.
[76] A similar
program exists in Massachusetts in which funds collected through an SBC are
used to provide price supports for RECs.
However, if such an approach is taken in Maine, the Commission
recommends that the guarantee be for the combined price of energy and RECs
because the situation can occur in which an increase in the price of energy
results in a reduction of the market price of RECs. The ability of a facility to obtain financing should depend on
the total revenue stream, not a component of total revenues.
[77] However,
the Commission does note that there is not a significant difference between
ratepayer funding and taxpayer funding in that it is essentially the same
people that provide the support.
[78] See,
MPUC Renewables Report at 29, Appendix I.
[79] Pine Tree
Zone benefits only apply to manufacturing operations and certain other industries
specified by law. The generation
of electricity is not generally considered to be manufacturing.
[80] Smaller
wind facilities are less economically viable and may not be able to take
advantage of the federal PTC.
[81] A
requirement that State government and universities meet an increasing
percentage of their power needs with renewable energy is an option discussed in
the DEP’s Climate Action Plan provided to the Legislature in 2004.
[82] Prior to
restructuring, utility resource planning and long-term acquisitions were under
direct control of the State and the risks of long-term power contracts (e.g.
stranded costs associated with qualifying facility contracts) fell upon
ratepayers.
[83] P.L. 2003, ch. 665 (major
substantive rulemaking required); Public Utilities Commission, Amendments to
Incorporate Renewable Resources into Standard Offer Supply, Docket No.
2004-606.
[84] The
Commission notes that dual environmental review is uncommon and only occurs
when a project is located in both DEP and LURC territory. Dual “environmental” review should not be
confused with a land use or zoning review that would typically occur by a
municipality or LURC in addition to the environmental review.
[85] The
Commission does not have the expertise or experience to make definitive
recommendations regarding the responsibilities of other agencies, but includes
suggestions in this report based on a wide variety of input and observations.
[86] The Commission understands that the DEP has
submitted legislation that would eliminate the requirement for it to permit
portions of a project located in LURC territory.
[87] The
environmental review process and associated requirements for wind facilities is
likely to become more certain and predictable as more projects are permitted.
[88] P.L.
2003, ch. 665, § 1 (codified at 35-A M.R.S.A. § 3210(7).