2009 ARRA/DWSRF Project Status
Status |
Public Water System |
Description |
Purpose |
Engineer |
Contractor |
Total Cost |
ARRA funds |
ARRA Reimb. to Date |
Reimbursed to Date |
Percent Complete |
Substantially Complete |
AUBURN WATER DISTRICT 2009-16 |
Water Main Rehabilitation & Improvements |
Address Aging Infrastructure |
Camp, Dresser, & McKee |
W. Walsh Company |
$500,000.00 |
$242,000.00 |
$242,000.00 |
$500,000.00 |
100% |
Under Construction |
AUBURN WATER DISTRICT 2009-17A |
Design & Construct New Water Treatment Facility Phase I and II |
Compliance with LT2ESWTR |
Camp, Dresser & McKee |
Camp, Dresser & McKee |
$4,120,900.00 |
$2,060,450.00 |
$1,238,020.73 |
$1,238,020.73 |
30% |
Under Construction |
GREATER AUGUSTA UTILITY DISTRICT 2009-13 |
Water Main Replacement Clifton St |
Replace Aging Infrastructure |
Woodard & Curran |
D & C Construction |
$190,000.00 |
$0 |
|
$178,889.78 |
100% |
Under Construction |
BANGOR WATER DISTRICT 2009-6 |
Conceptual Study on LT2 |
Compliance with LT2ESWTR |
Black & Vech |
Study Only |
$236,000.00 |
$236,000.00 |
$226,890.00 |
$226,890.00 |
75% |
Under Construction |
BANGOR WATER DISTRICT 2009-7 |
Water Storage Tank Replacement |
Aging Infrastructure and Improved Water Quality |
Wright Pierce |
Pre-Load Constr. |
$1,850,790.00 |
$904,110.92 |
$904,110.92 |
$1,149,401.67 |
70% |
Substantially Complete |
BATH WATER DISTRICT 2009-8 |
Water Main Looping |
Resolve Dead Ends |
Wright Pierce |
Ray Labbe & Sons |
$621,330.00 |
$303,519.71 |
$303,519.71 |
$609,080.33 |
100% |
Substantially Complete |
BELFAST WATER DISTRICT 2009-9 |
Water Main Replacement |
Replace Aging Infrastructure |
Dirigo Engineering |
George C. Hall & Sons |
$1,306,000.00 |
$637,981.00 |
$637,981.00 |
$1,146,617.71 |
100% |
Substantially Complete |
BERWICK WATER DEPARTMENT 2009-20 |
Water Main Replacement |
Replace Aging Infrastructure |
Civil Consultants |
Mick Construction |
$849,710.00 |
$415,083.33 |
$415,083.33 |
$661,050.33 |
100% |
Under Construction |
Bingham Water District 2009-10 |
Water Main Replacement & Looping |
Replace Aging Infrastructure & Improve Water Quality |
Dirigo Engineering |
Joseph Buchannan Construction |
$334,000.00 |
$0 |
|
$334,000.00 |
90% |
Substantially Complete |
BOWDOINHAM WATER DISTRICT 2009-25 |
New Well |
Provide Redundant Supply Well |
Wright Pierce |
Boart Longyear |
$149,000.00 |
$72,786.50 |
$72,786.50 |
$143,658.92 |
100% |
Substantially Complete |
BREWER WATER DEPARTMENT 2009-1 |
Interconnection with Adjacent Water System |
Provide Redundant Facilities |
Mike Riley |
Lou Silver, Inc |
$510,000.00 |
$0 |
|
$404,933.52 |
100% |
Under Construction |
AQUA MAINE,INC. CAMDEN & ROCKLAND DIV 2009-4 |
Water Treatment Plant |
Resolve Non-Acute Contamination |
Wright Pierce |
Apex & Son |
$3,621,868.00 |
$1,752,984.11 |
$1,752,984.11 |
$3,403,834.49 |
80% |
Substantially Complete |
Aqua Maine, Inc. Camden & Rockland Div 2009-5 |
New Storage Tank |
Replace Aging Infrastructure |
Wright Pierce |
Caldwell |
$990,379.00 |
$479,343.44 |
$479,343.44 |
$915,156.20 |
100% |
Under Construction |
Calais - ME 2009-12 |
New Storage Tank |
Replace Aging Infrastructure |
Olver Associates |
Sargent Corp |
$261,000.00 |
$0 |
|
$240,867.15 |
100% |
Under Construction |
Calais - ME 2009-12A |
Water Main Replacement |
|
Olver Associates |
Sargent Corp |
$44,500.00 |
$0 |
|
$17,841.27 |
60% |
Substantially Complete |
Kennebec Water District 2009-14 |
Water Main Replacement |
Replace Aging Infrastructure |
In-house |
T.W. Clark |
$409,640.50 |
$409,640.50 |
$337,155.15 |
$363,208.28 |
100% |
Under Construction |
LAKE ARROWHEAD COMMUNITY, INC. 2009-29 |
Water Main Replacement |
Replace Aging Infrastructure |
Wright Pierce |
In house |
$180,000.00 |
$180,000.00 |
$121,200.77 |
$121,200.77 |
90% |
Under Construction |
LEWISTON WATER & SEWER DIVISION 2009-17L |
Construct New Water Treatment Facility Phase I & II |
Compliance with LT2ESWTR |
Camp, Dresser, & McKee |
Camp, Dresser, & McKee |
$3,870,900.00 |
$1,935,450.00 |
$1,471,202.29 |
$1,471,202.29 |
25% |
Under Construction |
OLD TOWN WATER DISTRICT 2009-33 |
Treatment Facility Upgrades |
Rehabilitate Aging Infrastructure-enhance treatment |
Weston & Sampson |
T Buck Constr. |
$584,205.00 |
$175,860.00 |
$175,860.00 |
$360,000.00 |
90% |
Substantially Complete |
PASSAMAQUODDY WATER DISTRICT 2009-36 |
Water Main Replacement |
Replacement Aging Infrastructure |
A.E.Hodsdon Consulting |
S.H. Bridges Constr. |
$1,500,000.00 |
$1,500,000.00 |
$1,453,031.88 |
$1,459,103.02 |
100% |
Substantially Complete |
PORTLAND WATER DISTRICT 2009-38 |
Water Main Replacement William Clark Dr |
Replace Aging Infrastructure |
In-house |
Grondin & Sons |
$353,173.21 |
$353,173.21 |
$348,620.33 |
$310,506.59 |
100% |
Substantially Complete |
PORTLAND WATER DISTRICT 2009-39 |
Water Main Replacement Ray St |
Replace Aging Infrastructure |
In-house |
R.J. Grondin |
$410,314.50 |
$410,314.50 |
$388,006.66 |
$388,006.66 |
100% |
Substantially Complete |
PORTLAND WATER DISTRICT 2009-40 |
Water Main Replacement Scott Dyer Rd |
Replace Aging Infrastructure |
In-house |
Foglio, Inc. |
$142,102.04 |
$142,102.04 |
$141,870.98 |
$141,870.98 |
100% |
Substantially Complete |
PORTLAND WATER DISTRICT 2009-41 |
Water Main Replacement Brighton & Vannah Ave |
Replace Aging Infrastructure |
In-house |
Shaw Brothers |
$895,300.92 |
$895,300.92 |
$831,094.45 |
$831,094.45 |
100% |
Substantially Complete |
Portland Water District - 2009-42 |
Storage Tank Rehabilitation-Coating System |
Rehabilitation of Infrastructure |
In-house |
Marcel A. Payeur |
$384,722.99 |
$384,722.99 |
$346,722.99 |
$346,722.99 |
100% |
Substantially Complete |
Portland Water District - 2009-43 |
Main Replacement Hancock, Middle, Gilman, A St |
Replace Aging Infrastructure |
In-house |
Peters Construction |
$222,729.21 |
$222,729.21 |
$202,599.21 |
$202,599.21 |
100% |
Substantially Complete |
PORTLAND WATER DISTRICT 2009-44 |
Water Main Replacement Clifton St |
Replace Aging Infrastructure |
In-house |
Storey Brothers |
$371,000.00 |
$371,000.00 |
$350,592.73 |
$350,592.73 |
100% |
Substantially Complete |
PORTLAND WATER DISTRICT 2009-45 |
Water Main Replacement Read St |
Replace Aging Infrastructure |
In-house |
Gorham Sand and Gravel |
$297,075.00 |
$43,999.67 |
$43,999.67 |
$297,075.00 |
100% |
Substantially Complete |
PORTLAND WATER DISTRICT 2009-47 |
Water Main Replacement Oak, Berkeley, E. Gridge St |
Replace Aging Infrastructure |
In-house |
Glidden, Excv & Pav. |
$730,518.03 |
$730,518.03 |
$730,518.03 |
$730,518.03 |
100% |
Substantially Complete |
PORTLAND WATER DISTRICT - 2009-49 |
Water Main Replacement Elizabeth St |
Replace Aging Infrastructure |
In-House |
Dearborn Const. |
$155,391.21 |
$155,391.21 |
$147,393.13 |
$147,393.13 |
100% |
Substantially Complete |
PORTLAND WATER DISTRICT - 2009-51 |
Gorham Transmission Main |
Redundant Transmission Lines & Resolve low pressure |
In-House |
Dearborn Const. |
$544,842.69 |
$544,842.69 |
$544,842.69 |
$544,842.69 |
100% |
Substantially Complete |
RICHMOND UTILITIES DISTRICT 2009-54 |
Backup Well & Tank Circulation |
Redundancy and Tank Circulation |
Wright Pierce |
Boart Longyear |
$193,000.00 |
$94,280.50 |
$94,280.50 |
$189,095.12 |
100% |
Substantially Complete |
Yarmouth Water District 2009-15 |
Water main replacement |
|
Wright Pierce |
R.J.Grondon |
$648,358.12 |
$194,507.44 |
$194,507.44 |
$538,736.96 |
100% |
Under Construction |
MADAWASKA WATER DISTRICT 2009-31 |
Replace Booster PS & PSV Equipment |
Address Aging Infrastructure & Low Pressure |
Wright Pierce |
Penta Corp. |
$313,900.00 |
$153,340.15 |
$49,416.88 |
$49,416.88 |
20% |
Under Construction |
SOUTHWEST HARBOR WATER DEPT 2009-60 |
Emergency Generation for two locations |
Back-up power generation |
Olver Associates |
Sargent Corp |
$400,000.00 |
$195,400.00 |
$195,400.00 |
$351,819.91 |
80% |
Under Construction |
PRESQUE ISLE WATER DISTRICT 2009-52 |
UV Treatment Unfiltered Source |
Compliance with LT2ESWTR |
Wright Pierce |
Penta Corp. |
$560,000.00 |
$302,400.00 |
$121,656.31 |
$121,656.31 |
|
Under Construction |
PORT CLYDE WATER DISTRICT 2009-3 |
Booster Station |
Resolve Low Pressure Problems |
Dirigo Engineering |
Penobscot Co. |
$233,000.00 |
$0 |
|
$193,026.69 |
100% |
Under Construction |
SANFORD WATER DISTRICT 2009-56 |
Tank Mixing, Storage Tank Disinfection, & Station Upgrades |
Compliance with TCR Rule, improve water quality. |
Wright Pierce |
Apex |
$877,100.00 |
$405,476.00 |
$405,476.00 |
$793,540.38 |
80% |
Under Construction |
PITTSFIELD WATER DEPT. 2009-37 |
Install Finished Water Pump at Treatment Plant |
For Redundant Pumping Systems |
Olver Associates |
T. Buck Construction |
$103,000.00 |
$103,000.00 |
$81,168.32 |
$81,168.32 |
90% |
Under Construction |
ORONO-VEAZIE WATER DISTRICT 2009-34 |
Water Treatment Plant Upgrades |
Operational Efficiency |
Weston & Sampson |
Penta Corp |
$3,600,000.00 |
$1,284,458.07 |
$1,284,458.07 |
$1,935,597.92 |
40% |
Substantially Complete |
GREAT SALT BAY SANITARY DISTRICT 2009-28 |
Water Main Replacement |
Replace Aging Infrastructure |
Wright Pierce |
Penta Corp. |
$45,640.00 |
$0 |
|
$45,640.00 |
100% |
Under Construction |
PRINCETON WATER DISTRICT 2009-53 |
Transmission Main to Consolidate |
Resolve Acute Contamination |
Dirigo Engineering |
S.E. MacMillan |
$412,800.00 |
$199,795.20 |
$199,795.20 |
$320,753.23 |
90% |
Receiving Bids |
ST FRANCIS WATER DISTRICT 2009-61 |
New Source |
Resolve DBPs |
Woodard and Curran |
|
$349,423.00 |
$0 |
|
$55,120.49 |
|
Under Construction |
AQUA MAINE,INC. SKOWHEGAN DIVISION 2009-62 |
Water Main Replacement |
Replace Aging Infrastructure |
In House |
T.W. Clark Inc |
$260,865.00 |
$126,258.66 |
$126,258.66 |
$188,964.37 |
80% |
Under Construction |
NICHOLS TRAILER PARK 2009-32 |
New Supply |
Resolve Non-Acute Contamination (Uranium) |
Snowden Consulting |
Littlefield Construction |
$193,000.00 |
$0 |
|
$193,000.00 |
70% |
Under Construction |
EAST VASSALBORO WATER COMPANY LLC 2009-65 |
New water supply |
Decreasing Capacity of Existing Wells |
AE Hodsdon Engineering |
|
$154,020.00 |
$0 |
|
$100,687.50 |
60% |
Under Construction |
WINTERPORT WATER DISTRICT 2009-66 |
Install Backup Well |
Provide Supply Redundancy |
Dirigo Engineering |
|
$128,000.00 |
$0 |
|
$57,975.44 |
|
Substantially Complete |
SANFORD WATER DISTRICT 2009-64 |
Water Main Replacement & Looping |
Eliminate dead end & bleeder, loop main, end freezing. |
Wright Pierce |
Foglio Inc |
$680,000.00 |
$0 |
|
$489,845.22 |
80% |
Under Construction |
CALAIS WATER DEPT 2009-63 |
Water Main Replacement |
Replace Aging Infrastructure & Address Low Pressure |
Olver Associates |
Peasley & OHalloran |
$1,147,000.00 |
$0 |
|
$277,172.54 |
|
Under Construction |
PASSAMAQUODDY WATER DISTRICT 2009-35 |
Treatment & GW Source Study |
Resolve DBPs |
A.E.Hodsdon Consulting |
|
$57,000.00 |
$57,000.00 |
$35,567.08 |
$44,963.94 |
25% |
Under Construction |
BRUNSWICK / TOPSHAM WATER DISTRICT 2009-11 |
Treatment Facility Upgrades |
Compliance with Stage 2 D/DBP |
Wright Pierce |
T. Buck Construction |
$560,000.00 |
$0 |
|
$361,531.72 |
80% |
Under Construction |
BREWER WATER DEPARTMENT 2009-2 |
Redundant Intake Structure |
Provide Redundant Facilities |
Mike Riley |
Lou Silver, Inc |
$283,000.00 |
$0 |
|
$346,755.13 |
60% |
Under Construction |
SOUTHWEST HARBOR WATER DEPT. 2009-59 |
Treatment - Add Aeration, move intake |
DBP Reduction |
Olver Associates |
Sargent Corp |
$554,000.00 |
$315,780.00 |
$315,780.00 |
$553,261.00 |
90% |
Under Construction |
KENNEBUNK, KENNEBUNKPORT, & WELLS - 2009-67 |
Water Main Replacement |
Update infrastructure |
In-house |
In-house |
$1,949,180.00 |
$0 |
|
$478,536.46 |
20% |
|