Project Schedule
- Open House/Preliminary Public Hearing 11/17/22
- Plan impact Complete - January 2024
- Formal Public Meeting - September 2024
- Right of way process begins
- Final Mapping
- Appraisals
- Negotiations
- Project Plans, Specs & Estimate - February 2026
- Project advertise - March2026
- Construction Complete - Fall 2028/Spring 2029