Ticonic Bridge Photo Gallery

February 2025

Throughout February, crews made steady progress on the project. Butler successfully completed the removal of the arch bridge (spans 1-4), marking a major milestone. Ranger backfilled Abutment 2 up to the approach slab grade, preparing the area for the next phase of construction.

Meanwhile, Cianbro continued erecting the downstream gantry towers and truss while demobilizing the upstream gantry truss and towers. Efforts also focused on clearing arch bridge debris from the river and installing the upstream bridge rail.

January 2025

Throughout January crews have been making significant progress on the project, with three of four arches removed and work ongoing on the final arch over the impoundment. CMP duct bank work continues, along with north gantry removal and installation of the south gantry, with two sections received. Water line installation and tie-ins on the Winslow side are progressing, while curb work, including keyway stripping and finishing, is underway.